- RES/RER-Airport question changes from 2 to 4 miles
- RES/RER-New checkbox in the Floodplain/Regulatory Floodway section regarding MoDOT property
- RES/RER-Changes to Consultant/Contractor/Administrator privileges and login. Each consultant/contractor company will only be allowed in the system once as Admin, then individuals are Representatives. Admin will be able to see all Reps and projects. Admin can edit or change Admin information or other company information.
- RES/RER-Ability to save a “draft” RES/RER without filling out all the required fields, once ready for submittal, will prompt to fill out all required fields.
- RER-Airport question text change from “district” to “LPA”.
- RES/RER-In the NEPA response section, change “SHPO/4(f)” to “SHPO” only.
- RER-Change “Submit draft to district” to “Submit review” and change “Submit to districts” to “Submit final”.
- RER-Add “LPA” to title of RER
- RES/RER-Change “Help” to “Instructions”.
- RES/RER-Delete “Explain the purpose of the request”. There isn’t normally a different purpose for the request than NEPA clearance, and if so, could be identified elsewhere.
- RER-Delete “Changes to the project since the last RER submitted? If yes, explain”. There is only one RER so this question is not necessary.
- RER-Change “NEPA Approval Date” to “NEPA Approval/A-date”.
- RER-Add PCE# with NEPA Class and “all environmental issues clear” date.
Posted 8/8/2018
** UPDATED 8/10/2018**
Published On