Where: Republic Road bridge over U.S. Route 60 between Campbell Avenue & Kansas Expressway and Quail Creek Avenue west of the bridge are OPEN in Springfield
When: 2 p.m. Thursday, December 12
What: Contractor crews resurfaced the bridge deck (driving surface), installed new barrier wall and worked on the bridge drainage system underneath the bridge
Traffic Impacts:
- Republic Road bridge intermittent lane drops expected for the next few weeks as crews complete the project
- Signs and message boards will alert drivers approaching the work zone
- Drivers will need to follow the signed detour or seek an alternate route to avoid the work zone
- Check MoDOT’s Traveler Information Map for road closings/traffic impacts
Weather and/or construction delays will alter the work schedule.
Project information
- Contractor: KCI Construction, Springfield
- Estimated total cost: $1,136,490
END
For more information, call MoDOT in Springfield at 417-895-7600 or visit www.modot.org/southwest