Dent County bridge project starting this week

Missouri Route 19 Standing Rock Creek Bridge replacement project

JEFFERSON CITY, Mo – A bridge replacement project on Missouri Route 19 over Standing Rock Creek in Dent County began this week. The bridge is to remain open throughout construction. The three phases of the project will impact traffic in different ways:

Phase 1 – Construction of new bridge and roadway alongside the existing structure.

  • Short-term, intermittent flagging operations.

Phase 2 - Construction of northbound lane of realigned Route 19

  • Temporary traffic signals with traffic narrowed to a single lane.

Phase 3 - Construction of southbound lane of realigned Rte. 19

  • Temporary traffic signals with traffic narrowed to a single lane.

 

The construction is expected to be complete by May 1, 2025. To learn more about the project and why MoDOT is replacing the bridge, follow the link: https://www.modot.org/missouri-route-19-bridge-replacement-over-standing-rock-creek-dent-county.

MoDOT asks all motorists to work with us by buckling up, putting your phone down, obeying all traffic signs, and slowing down and moving over in work zones. Motorists are advised to use extra caution through work zones, obey all traffic signs, and avoid any distractions.  

For traffic updates or other transportation-related matters, please call 1-888-ASK-MoDOT (275-6636) or visit our Traveler Information Map. Information is also available 24/7 via social media. Follow the MoDOT Central Missouri District on social media:

Facebook | X (Twitter) | Instagram  

Take the Challenge! Buckle Up/Phone Down 

###

Districts Involved
Central
MODOT Newsroom

The newsroom is a one-stop shop for media partners to find their local and statewide communications contacts and news releases, as well as download department leadership portraits and other media.

Visit the Newsroom
Real Time Traffic

Monitor real time traffic with our online traffic map.