What: Lane Closure on Missouri Route 76 eastbound bridge north of Branson
When: 7 a.m. – 4 p.m. Thursday & Friday, December 5 & 6
Details: Contractor crews to work on the Missouri Route 76 eastbound bridge to install rock.
Contractor crews plan to rehabilitate the westbound Missouri Route 76 bridge in January 2025. More information will be released as the contractors schedule gets confirmed for the westbound bridge work.
Traffic Impacts:
- Lane Closure on Missouri Route 76 eastbound bridge north of Branson
- Both lanes will be open during nighttime hours
- Crew and equipment close to traffic
- Drivers will encounter flaggers where crews are working
- No signed detour. Drivers should find alternate routes.
- Signs and message boards will alert drivers approaching the work zones
- Check MoDOT’s Traveler Information Map for road closings/traffic impacts
Weather and/or construction delays could alter the work schedule.
Project Information:
- Contractor: Emery Sapp & Sons, Inc., Columbia
- Total project cost: $850,000
- Contract completion date: May 16, 2025
END
For more information, call MoDOT in Springfield at 417-895-7600 or visit www.modot.org/southwest
Follow MoDOT's Southwest District: Facebook | X | Instagram |YouTube
Take the Challenge! Buckle Up/Phone Down