JEFFERSON CITY, Mo. – The following is a list of general highway maintenance and construction work planned in the mid–Missouri area Dec. 2 – 8, 2024. Weather conditions may postpone scheduled work. Many projects will include lane closures which could cause delays.
All Counties
Moving operations such as pothole patching, mowing, brush cutting, and pavement repair continue in various locations. Motorists should travel with care and be alert for slow – moving equipment.
All work is weather permitting, and schedules are subject to change.
Boone County
Route M – Roadside work planned Dec. 2 – 6 at Route MM. One lane will remain open, and crews will flag traffic through the work zone.
I-70 – Bridge construction continues for the new Rocheport Bridge near mile marker 115. The new eastbound bridge is scheduled to open to traffic in December 2024.
Route TT – Upgrades to pedestrian facilities continue on Broadway between Route ZZ and Silvey Street. The work is being done by the city of Columbia. The project is scheduled for completion in December 2024.
U.S. Route 63 – Bridge construction continues on U.S. Route 63 between the Broadway overpass and Conley Road underpass in Columbia. U.S. Route 63 will remain open but in a head-to-head configuration with narrowed lanes and reduced speeds. This traffic pattern is expected to be in place through late 2025. The bridge construction is part of the Improve I-70 program. Learn more at modot.org/improvei70/columbiakingdomcity.
I-70 – New pavement construction continues in Columbia from Route B (Paris Road) to U.S. Route 63 through January 2027 as part of the Improve I-70 program. Motorists can expect intermittent and long-term lane closures for the duration of the project. Learn more at modot.org/improvei70/columbiakingdomcity.
Callaway County
Route BB – Culvert replacement planned Dec. 2. at County Road 430. The road will be CLOSED 8 a.m. to 3 p.m.
Eastbound U.S. Route 54 – Routine bridge inspection planned Dec. 2 - 5 over the Missouri River. One lane will be closed 8 a.m. to 3 p.m., daily.
Route Z – Culvert replacement planned Dec. 3. from Route JJ to County Road 115. The road will be CLOSED8 a.m. to 3:30 p.m.
Missouri Route 94 – Shoulder work planned Dec. 3 – 5 from County Road 453 to County Road 458. One lane will remain open, and crews will flag traffic through the work zone.
Route Z – Culvert replacement planned Dec. 4. from County Road 119 to County Road 108. The road will be CLOSED 8 a.m. to 3:30 p.m.
Route TT – Culvert replacement planned Dec. 6. at County Road 498. The road will be CLOSED 8 a.m. to 3 p.m.
U.S. Route 54 – Guardrail work continues from Jefferson City to Kingdom City. Single-lane closures will occur at varying times, depending on the location. Expect delays during morning/evening rush hours. The project is expected to continue through January 2025.
I-70 – New pavement construction continues from the Boone County line to Kingdom City (near mile marker 145) as part of the Improve I-70 Program. Motorists can expect intermittent and long-term lane closures for the duration of the project. Learn more at modot.org/improvei70/columbiakingdomcity
Camden County
Route D – Culvert replacements planned Dec. 5 – 6 in several locations. The road will be CLOSED daily, 8 a.m. to 3:30 p.m
- Dec. 5
- closed from Aubrey Bell Road to Brush Arbor Road.
- Dec. 6
- closed 1.5 miles south of U.S. Route 54.
Cole County
Outer Road 50 (Country Club Drive) – Pavement repair planned Dec. 2 – 3 at Hunters Run Road. One lane will remain open, and crews will flag traffic through the work zone.
Eastbound U.S. Route 54 – Routine bridge inspection planned Dec. 2 - 5 over the Missouri River. One lane will be closed 8 a.m. to 3 p.m., daily.
Cooper County
Route K – Bridge maintenance planned Dec. 2 – 6 at Blackwater River Creek bridge. One lane will remain open, and crews will flag traffic through the work zone.
I-70 – Bridge construction continues for the new Rocheport Bridge near mile marker 115. The new eastbound bridge is scheduled to open to traffic in December 2024.
Crawford County
Missouri Route 8 – Roadside work planned Dec. 2 – 6 from Missouri Route 19 to Route T. One lane will remain open, and crews will flag traffic through the work zone.
Missouri Route 49 – Roadside work planned Dec. 2 – 6 from Missouri Route 19 to Route Y. One lane will remain open, and crews will flag traffic through the work zone.
Route M – Roadside work planned Dec. 2 – 6 from Missouri Route 8 to Route YY. One lane will remain open, and crews will flag traffic through the work zone.
Route HH – Culvert replacement planned Dec. 2 – 6. One lane will remain open, and crews will flag traffic through the work zone.
Howard County
Route W – Culvert replacement planned Dec. 2 – 6 from County Road 400 to County Road 402. One lane will remain open, and crews will flag traffic through the work zone.
Laclede County
Route VV – Culvert replacement planned Dec. 2. from Lonesome Road to Missouri Route 5. The road will be CLOSED, 8:30 a.m. to 2:30 p.m.
Route O – Bridge maintenance planned Dec. 2 – 6 at the Gasconade River bridge. One lane will remain open, and crews will flag traffic through the work zone.
Route D – Culvert replacements planned Dec. 2 – 4 in several locations. The road will be CLOSED daily, 8 a.m. to 3:30 p.m.
- Dec. 2
- closed north of Eldridge, from Navy Drive to Kansas Road.
- closed at Laurel Road.
- Dec. 3
- closed 0.5 miles north of Laurel Road.
- closed at Nathan Lane.
- Dec. 4
- closed at Nathan Lane.
Route E – Culvert replacement planned Dec. 5 – 6. The road will be CLOSED from Bluff Trail Road to Route NN, 8:30 a.m. to 2:30 p.m. daily. Motorists must use an alternate route.
Maries County
Missouri Route 42 – Roadside work planned Dec. 2 – 4 from the city of Vienna to the city of Belle. One lane will remain open, and crews will flag traffic through the work zone.
Route C – Roadside work planned Dec. 2 – 4 from Missouri Route 28 to Route H. One lane will remain open, and crews will flag traffic through the work zone.
Moniteau County
U.S. Route 50 – Roadside work planned Dec. 2 – 6 from Missouri Route 87 to Bahner Quarry Road. One lane will remain open, and crews will flag traffic through the work zone.
Phelps County
Route F – Culvert replacement planned Dec. 2 – 6 from County Road 3150 to County Road 3170. One lane will remain open, and crews will flag traffic through the work zone.
Route T – Pothole patching planned Dec. 2 – 6. One lane will remain open, and crews will flag traffic through the work zone.
Route HH – Culvert replacement planned Dec. 2 – 6 from County Road 8040 to County Road 8070. One lane will remain open, and crews will flag traffic through the work zone.
I-44 – Road resurfacing and reconstruction continues from Exit 186 in Rolla to Exit 195 in St. James. Expect overnight lane closures, westbound only, from U.S. Route 63 to Route 68. An 11-foot width restriction is in place. The end date for the project is yet to be determined based on concrete quality issues that will need to be corrected. Learn more: https://www.modot.org/node/54613
Pulaski County
Route W – Roadside work planned Dec. 2 at Rim Drive. One lane will remain open, and crews will flag traffic through the work zone.
Route BB – Roadside work planned Dec. 4 from Missouri Route 133 to Boren Drive. One lane will remain open, and crews will flag traffic through the work zone.
MoDOT asks all motorists to work with us by buckling up, putting your phone down, obeying all traffic signs, and slowing down and moving over in work zones.
For more information about MoDOT projects, traffic updates, or other transportation–related matters, please visit our Traveler Information Map at http://traveler.modot.org/ or call our 24–hour Customer Service Center at 1–888–ASK–MoDOT (888 275–6636). While at modot.org, sign up for work zone updates sent directly to your inbox. Information is also available 24/7 by connecting with us on social media: