Counties Impacted
Jackson
Completed

Construction Updates

Complete
Project Update: 02/28/19

A new completion date has been set for the project. Crews expect to be done with the new DDI (Diverging Diamond Interchange) project by July 31, 2019.  

milestone_icon
Complete
Update 7/27/18 

Crews will close the left lane of eastbound Route 210 and I-435 beginning Monday, July 30 through Wednesday, August 8 (including weekends) for setting barriers, excavation and drill shaft installation work. Crews will also close the left lane of westbound Route 210 at I-435 from 9 a.m. to 4:30 p.m. daily during the same time period for bridge work.

milestone_icon
Complete
Update 7/9/18 

Crews will close westbound 210 Hwy at northbound I-435 from 11pm Friday, July 13 until Monday, July 16 for bridge demo work. Also closed during that time period: Eastbound 210 Hwy at Chouteau Traffifcway, the ramp from 210 Hwy to southbound I-435 and the ramp from southbound I-435 to 210 Hwy. These closures are in preparation for demolishing the southbound bridge over 210 Hwy.

milestone_icon
Complete
Update 7/12/18

 Crews have rescheduled work in preparation for the demolition of the southbound I-435 Bridge over Route 210. Crews will reduce southbound I-435 at Route 210 to one lane from 9a until 3p Friday, July 13 for pavement marking and shifting traffic to a head-to-head configuration. Crews will southbound I-435 traffic to the northbound I-435 lanes. This work was originally scheduled for Thursday, July 12.

milestone_icon
Complete
Update 6/25/18 

Construction work continues on the building of the new westbound lanes of Route 210, west of the interchange. In order to construct these lanes, crews will need to move the westbound traffic onto a head-to-head configuration on the new eastbound lanes, which were constructed earlier this year.

milestone_icon
Complete
Update 3/1/18 

Crews will close all northbound and southbound lanes of I-435 at Route 210 beginning at 10 p.m. Friday, March 2 through 5 a.m. Monday, March 5 for demolition of the now-closed flyover ramp. Traffic will be detoured to I-35 for both directions.

milestone_icon
Complete
Update 2/26/18 

Crews are set to resume work on the project. The biggest impact to date will be the permanent closure of the flyover ramp from northbound I-435 to westbound Route 210 (Exit 55). Crews will close the ramp at 9 a.m. Wednesday, Feb. 28. The closure is in preparation for demolition of the ramp which is set to happen the weekend of March 2. Motorists wishing to travel westbound will need to exit at Route 210 and I-435 and turn left at the temporary traffic signal.

milestone_icon
Complete
Update 11/15/17 

Crews have returned I-435 and Route 210 very close to its original configuration for the winter months. This project will resume construction in early spring or when temperatures allow.

milestone_icon
Complete
Project Update 4/30/19

Crews will close the right lane of SB I-435 between Parvin Road and Route 210 from 9 a.m. until 3 p.m. Wednesday, May 1 for paving work. 

 

Crews will close the right lane of SB I-435 between Parvin Road and the Missouri River Bridge from 7 p.m. Friday, May 3 until 7 p.m. Saturday, May 4 for traffic pattern change.

 

Crews will close the ramp from Route 210 to SB I-435 from 10:30 p.m. Friday, May 3 until 7 p.m. Saturday, May 4 for traffic pattern change.

Crews will close the ramp from Parvin Road to southbound I-435 from 10 a.m. until 7 p.m. Saturday, May 4 for traffic pattern change. 

milestone_icon
Complete
Project Update 5/10/19

Crews will close the left lane of eastbound Route 210 at I-435 from 7 a.m. until 3 p.m. Monday, May 13 for paving work.

 

Crews will close the left lane of northbound I-435 between Front St. and Route 210 beginning Thursday, May 16 and will remain closed for approximately 30 days. This will lead up to a traffic pattern change.  

milestone_icon
Complete
Project Update: 5/16/19

Crews will reopen the center lane of northbound I-435 between Front St. and Route 210 beginning at 3 p.m. Friday, May 17.

 

Crews will close the left lane of northbound I-435 between Front St. and Route 210 beginning at 3 p.m. Friday, May 17 and will remain closed for approximately 30 days.... for median barrier work. 

milestone_icon
Complete
Project Update: 5/31/19

Crews will reduce eastbound Route 210 at I-435 to one lane beginning Tuesday, June 4 and will remain that way for at least 30 days for interchange reconstruction work. 

milestone_icon
Complete
Project Update: 6/12/19

Crews will open all lanes of eastbound Route 210 at I-435 beginning Friday, June 14. Originally, one lane of eastbound Route 210 at I-435 was to remain closed for at least 30 days for interchange reconstruction work. That work was finished ahead of schedule, due in part to favorable weather conditions. 

milestone_icon
Complete
Project update: 6/18/19

The weekend of 6/21 through 6/23 crews will close several lanes and ramps for pavement repair work. These closures will greatly impact businesses in the area. 

Crews will close 2 lanes of northbound I-435 between Route 210 and Parvin Rd. from 7 p.m. Friday, June 21 through 2 p.m. Saturday, June 22.

Crews will close the right lane of southbound I-435 between 48th St. and Route 210 from 8 p.m. Friday, June 21 through 3 p.m. Saturday, June 22.

Crews will close the ramp from northbound I-435 to Parvin Rd. from 10 p.m. Friday, June 21 through 1 p.m. Saturday, June 22.

Crews will close the ramp from Parvin Rd. to southbound I-435 from 10 p.m. Friday, June 21 until 1 p.m. Saturday, June 22. 

 

 

milestone_icon
Complete
Project Update: 7/9/19

Crews will close the right lane of EB Route 210 at I-435 from 7a-3p Wed. July 10 and again Thursday, July 11 for paving work.

Crews will close the right lane of SB I-435 between 48th St. and Route 210 from 9a-3p Thursday, July 11 for installation of KC Scout cameras. 

Crews will close two lanes of NB I-435 between Front St. and Route 210 from 7p Friday, July 12 through 6a Saturday, July 13 for pavement work. 

milestone_icon
Complete
Project Update: 7/12/19

Crews will close the right lane of eastbound Route 210 at I-435 from 7 a.m. until noon Saturday, July 13 for paving work 

Crews will close the right lane of eastbound Route 210 at I-435 from 7 a.m. until 3 p.m. Monday, July 15 for paving work 

Crews will close the left lane of westbound Route 210 at I-435 beginning at 9 a.m. Tuesday, July 16 and will continue for at least three weeks for paving work 

 

milestone_icon
Complete
Project Update: 7/22/19

Crews will close the right lane of eastbound Route 210 at I-435 from 7 a.m. until 3 p.m. Tuesday, July 23 for pavement work 

Crews will close two lanes of southbound I-435 between 48th St. and Route 210 from 9 a.m. until 3 p.m. Tuesday, July 23 for relocating temporary barriers.

Crews will close two lanes of northbound I-435 between Front St. and Route 210 from 9 a.m. until 3 p.m. Tuesday, July 23 for relocating temporary barriers

Crews will close two lanes of northbound I-435 between 48th and Route 210 from 7 p.m. Tuesday, July 23 until 5:30 a.m. Wednesday, July 24 for patching work 

 

milestone_icon
Complete
Project Update: 8/16/19

All northbound and southbound lanes of I-435 at Route 210 are open. This portion of the project is now complete. 

milestone_icon
Complete
Project Update: 9/20/19

Crews will close one lane of SB I-435 between Route 210 and Front St. for approximately 10 days for grading work. Crews will close one lane of NB I-435 between Front St. and Route 210 for approximately 10 days for grading work. 

milestone_icon

Click Here to See a Detailed Map of Scheduled Construction Activities. When viewing the map, you can click on a specific route/roadway and updated information will be given on what is happening regarding construction.

For a webcam view of the project, click on the link: 2ueBG4m

About this project

The Route 210 and I-435 interchange currently serves nearly 100,000 drivers per day.  This project will enhance capacity of I-435 by providing three continuous through lanes in each direction throughout the interchange. 

Route 210 is an important freight corridor that serves multimodal freight hubs and was last summer from two lanes to four lanes from Eldon Road to MO 291.  The new interchange will be able to accommodate the increased truck and vehicle traffic of Route 210. 

This project will also remove the two uncommon high speed ramps to enhance driver expectancy and safety. Ramp reconstruction will enhance safety by providing increased storage and better turning movements.  This project also includes the alteration of access at Randolph Road which will result in fewer traffic signal challenges and will improve safety. 

What is the project timeline?   

Construction began in the fall of 2016.

  • 2016- Construction of Great Midwest Drive and Randolph Road
  • 2017- Construction of NB/SB I-435 Bridges
  • 2019- Finish construction of Route 210 and Diverging Diamond  July 31