Where: Campbell Avenue CLOSED at night between Republic Road and the eastbound U.S. Route 60 ramps in Springfield
When: 8 p.m. – 6 a.m. Wednesday-Thursday night, July 10-11 & Thursday – Friday night, July 11-12
What: Contractor will CLOSE north and southbound Campbell Avenue under U.S. Route 60 at night from 8 p.m. – 6 a.m. Wednesday & Thursday, July 11 & 12. From 10 p.m. Thursday, July 11 until 6 a.m. Friday, July 12, westbound Route 60 traffic will be shifted down and over Campbell Avenue using the westbound Route 60 on and off-ramps. Crews are setting bridge girders for the U.S. ROUTE 60 (James River Freeway) Widening Project Between National Avenue & Kansas Expressway.
Traffic Impacts:
- Campbell Avenue CLOSED between Republic Road and the eastbound U.S. Route 60 ramps in Springfield, Wednesday & Thursday nights, July 10 & 11
- Westbound Route 60 traffic will be shifted down and over Campbell Avenue using the Westbound Route 60 on and off-ramps from 10 p.m. Thursday, July 11 until 6 a.m. Friday, July 12
- Route 60 (James River Freeway) Open in both directions
- Detours:
- Northbound Campbell Avenue traffic will be routed to eastbound Route 60
- Southbound Campbell Avenue traffic will be routed to east and westbound Republic Road
- Eastbound Route 60 exit ramp to Campbell Avenue will be routed to southbound Campbell Avenue
- Westbound Route 60 exit ramp to continue onto westbound Route 60 or northbound Campbell Avenue
- Signs and message boards will alert drivers approaching the work zone
- Drivers will need to follow the signed detour or seek an alternate route to avoid the work zone
- Check MoDOT’s Traveler Information Map for road closings/traffic impacts
Weather and/or construction delays will alter the work schedule.
Project information:
Contractor: Capital Paving & Construction LLC, Jefferson City
Total estimated cost: $21 million
- Intersection Improvements at Campbell Ave are a cost share with the City of Springfield
Project Webpage: https://www.modot.org/us-route-60-james-river-freeway-widening-project
Sign up for project updates: U.S. Route 60 (James River Freeway) Widening Project
END
For more information, call MoDOT in Springfield at 417-895-7600 or visit www.modot.org/southwest
Follow MoDOT's Southwest District: Facebook | X | Instagram | YouTube
Take the Challenge! Buckle Up/Phone Down