ST. JOSEPH, Mo. – A resurfacing project has begun on various routes in Daviess, Grundy, Harrison and Mercer counties. Herzog Contracting Corp., working with the Missouri Department of Transportation, expects to complete the project by mid-September. During resurfacing, each route will be closed in up to 2-mile sections. Motorists will need to seek an alternate route during the closures.
Planned resurfacing schedule:
- Mercer/Grundy Route A: July 18 - Aug. 2
- Mercer Route 145: Aug. 2 - Aug. 4
- Harrison/Mercer Route V: 4 - Aug. 14
- Daviess/Grundy Route P: 14 - Aug. 22
- Daviess/Harrison Route K: Aug. 22 - Sept. 6
Following resurfacing, crews will return to each route to install edge rock shoulders and add new pavement markings.
All work is weather-permitting, and schedules are subject to change.
Know before you go by visiting the MoDOT Traveler Information Map for work zone information and road conditions at http://traveler.modot.org/map/, or downloading from your smart phone’s app store.
MoDOT asks drivers to work with us by always buckling up, keeping your phone down, slowing down and moving over in work zones.
When visiting modot.org, sign up online for work zone updates. Information is also available 24/7 at 888-ASK-MODOT (275-6636) or by connecting with us on social media.
Facebook | Twitter | Instagram
Take the Challenge! Buckle Up/Phone Down
###
Governor’s Rural Roads Program
www.modot.org/governors-rural-roads-program