ST. JOSEPH, Mo. – An intersection improvement project on Grundy County Route 6 at the intersections of 30th Avenue and Route 146/W, located just west of Trenton, is underway and scheduled to begin the next stage of Phase 1 construction at the 30th Avenue intersection tomorrow, Wednesday, June 7. The Missouri Department of Transportation has contracted with Phillips Hardy, Inc. to complete the project which includes widening Route 6 at both intersections and constructing dedicated left and right turn lanes.
The project is being constructed in two phases following the below updated schedule:
- Phase 1: 30th Avenue intersection – crews have completed work on the eastbound lane of Route 6 and will be switching traffic on Wednesday, June 7, to begin construction of the westbound lane. Phase 1 is expected to be complete in mid-July. Access to/from north and south 30th Avenue will be closed during this phase.
- Phase 2: Route 146/W intersection – scheduled for mid-July through early October. Access to/from Route W will be closed during this phase. East and westbound traffic on Route 6 will still be able to access Route 146 to travel north towards Crowder State Park.
During each phase, Route 6 will be narrowed to one lane. Traffic will be directed through the work zone by temporary traffic signals. A 12-foot width restriction will be in place throughout the project.
To learn more, visit the projects webpage at: https://www.modot.org/grundy-county-route-6-intersection-improvements-project.
For more information about this and other MoDOT projects in your area, sign up online for work zone updates, visit modot.org/mo-go to view the online Traveler Information Map, or call 888-ASK-MODOT (275-6636). In addition, MoDOT provides updated information via social media.
Facebook | Twitter | Instagram
###
Project Webpage
https://www.modot.org/grundy-county-route-6-intersection-improvements-project