UPDATE: Buchanan and Andrew County pavement improvement project

Traffic to switch lanes at Frederick Boulevard Bridge

ST. JOSEPH, Mo. – Beginning tomorrow, April 25, motorists on southbound Buchanan County Interstate 29 can expect a lane change at the Missouri Route 6 (Fredrick Boulevard) Bridge in St. Joseph. Crews from Herzog Contracting Corp., contracted by the Missouri Department of Transportation, will switch southbound traffic from the outside driving lane to the inside passing lane from Gene Field Road to Route YY (Mitchell Avenue).

The pavement improvement project, which began in March, is still in the first stage of construction as crews finish concrete work under the bridge. The traffic switch of the northbound lanes is anticipated to occur this Thursday, April 27. The project has faced delays due to weather and pavement conditions. An updated full project schedule is shown below:

March 1 through mid-July:

Concrete replacement under Missouri Route 6 (Frederick Boulevard) Bridge. Motorists should expect delays.

  • All work will be completed during daylight hours, Monday through Saturday. The work zone will extend north and southbound from Gene Field Road to Route YY (Mitchell Avenue).
  • April 25-early July: Southbound traffic will be switched to be narrowed to one lane, around-the-clock in the inside passing lane. Outside driving lane will be closed.
  • April 27-mid-July: Northbound traffic will be switched to be narrowed to one lane, around-the-clock in the outside driving lane. Inside passing lane will be closed.

Early April through late August:

Guardrail and median cable improvements and roadway patching from south of Business Route 71 (Andrew County) to south of Route O (Buchanan County).

  • All work will be completed overnight from 6 p.m. to 7 a.m., Sunday through Friday. Intermittent lane closures will occur.

Mid-July through late October:

Pavement improvements from south of Business Route 71 (Andrew County) to south of Route O (Buchanan County).

  • All work will be completed overnight from 6 p.m. to 7 a.m. Sunday through Friday. Intermittent lane closures will occur.
  • Intermittent, overnight closures of the on/off ramps for resurfacing at the intersections of U.S. Route 169 (Exit 50), Frederick Boulevard (Exit 47), U.S. Route 36 (46 A/B), U.S. Route 69 (Exit 44) and I-229 (Exit 43). More information on the ramp closure schedule will be provided as information becomes available.

An 11-foot width restriction will be in place for all project work zones.

All work is weather-permitting, and schedules are subject to change. Know before you go by visiting the MoDOT Traveler Information Map for work zone information and road conditions at http://traveler.modot.org/map/, or downloading from your smart phone’s app store.

MoDOT asks drivers to work with us by always buckling up, keeping your phone down, slowing down and moving over in work zones.

When visiting modot.org, sign up online for work zone updates. Information is also available 24/7 at 888-ASK-MODOT (275-6636) or by connecting with us on social media. 