Resurfacing project to begin in Mercer, Grundy, Harrison and Worth counties

Part of Gov. Parson's Rural Road Program

ST. JOSEPH, Mo. – A resurfacing project on several routes in Mercer, Grundy, Harrison and Worth counties is scheduled to begin soon. Herzog Contracting Corp., working with the Missouri Department of Transportation, is scheduled to resurface 12 routes beginning Monday, April 3. The project is expected to be completed in late June 2023.

The project will be split with Herzog Contracting Corp. completing the five Harrison and Worth county routes, and their sub-contractor, Norris Asphalt Paving Co., completing the seven Grundy and Mercer County routes.

Crews will work daylight hours, Monday through Saturday. During construction each route will be closed in up to 2-mile segments. The roadways will reopen each evening.

Norris Asphalt Paving Co. plan to complete the seven Grundy and Mercer County routes following the below schedule:

  • Grundy County Routes C/B, Mercer County Routes U, JJ, D, C and Mercer/Grundy County Route NN – milling off existing pavement, April 3-7
  • Mercer County Route U – paving, April 10-14
  • Mercer County Route D – paving, April 17-21
  • Grundy County Route C/B – paving, April 24-28
  • Grundy/Mercer County Route NN – paving, May 1-12
  • Mercer County Route JJ – paving, May 12-15
  • Mercer County Route C – paving, May 15-24
  • Grundy County Routes C/B, Mercer County Routes U, JJ, D, C and Mercer/Grundy County Route NN – rock shoulders and pavement markings – May 25 – June 14

Herzog Contracting Corp. plan to complete the five Harrison and Worth County routes following the below schedule:

  • Harrison County Routes F, MM, T and Harrison/Worth County Route M – milling off existing pavement, April 12-13
  • Harrison/Worth County Route M – paving, April 17-25
  • Harrison County Route F – paving, April 26 – May 3
  • Harrison County Route T – paving, May 4-23
  • Harrison County Route MM – paving, May 24 – June 1
  • Harrison County Routes F, MM, T and Harrison/Worth County Route M – rock shoulders and pavement markings – June 5-26

All work is weather-permitting, and schedules are subject to change. Know before you go by visiting the MoDOT Traveler Information Map for work zone information and road conditions at http://traveler.modot.org/map/, or downloading from your smart phone’s app store.

More information can be found on the project webpage at: https://www.modot.org/low-volume-route-resurfacing-grundy-harrison-mercer-and-worth-counties.

This project is part of Gov. Parson’s Rural Road program. The state’s approved Fiscal Year 2023 budget provided an additional $100 million in General Revenue for work on Missouri’s low volume rural roads. Using asset management data, MoDOT has identified approximately 1700 lane miles of low volume roads ranked in Poor Condition. By next summer, these 113 locations will receive resurfacing treatments of hot mix asphalt to improve the road conditions.

MoDOT asks drivers to work with us by always buckling up, keeping your phone down, slowing down and moving over in work zones.

When visiting modot.org, sign up online for work zone updates. Information is also available 24/7 at 888-ASK-MODOT (275-6636) or by connecting with us on social media.

Facebook | Twitter | Instagram  

Take the Challenge! Buckle Up/Phone Down

###

Governor’s Rural Roads Program

www.modot.org/governors-rural-roads-program

Districts Involved
Northwest