Greene County – Drivers can expect lane closings on Missouri Route 13 in Greene when contractor crews resurface the state route starting the week of October 4, the Missouri Department of Transportation said.

Route 13 will receive a new asphalt driving surface between Norton Road in Springfield and the Greene/Polk County line. Work will be done during both daytime and nighttime hours.

This project includes resurfacing Route 13 between the Polk/Greene County line to St. Clair County Route UU north of Humansville. This portion of the project has not yet been scheduled. The total length of the project is 69 miles. This work was originally scheduled to begin in August, however, construction delays postponed the project.

Traffic Impacts:

  • ‘Round the clock lane closings where crews are resurfacing roadway
  • Crews and equipment close to traffic in areas
  • During higher traffic volume times, expect occasional delays
  • Drivers may need to seek alternate routes to get to their destinations

Weather and/or construction delays will alter the work schedule.

Capital Paving & Construction LLC, Columbia is doing the work for a low bid amount of $7 million.

The project is to be completed by late November 2021.

END 



(For more information, call MoDOT in Springfield at 417-895-7600 or visit
www.modot.org/southwest



(Follow MoDOT's Southwest District:
Facebook | Twitter | Instagram | YouTube)

(Take the Challenge! Buckle Up/Phone Down)

 

Districts Involved
Southwest