CLAY/JACKSON COUNTIES – The Missouri Department of Transportation will soon enter a new phase of the Buck O’Neil/US 169 Missouri River Bridge replacement project. Phase One-B will cause extensive closures. All work is weather dependent.

Crews will reduce Beardsley Rd. to one lane between 5th and 4th St. from 11am until 5pm, Monday, September 20 for crane work (crane assembly). A flagger will be in place to direct traffic

Crews will close the on ramp from northbound Richards Rd. to northbound 169 Highway, beginning at 6am, Monday, September 27 and continuing until Wednesday, November 17 for grading, new drainage installation and ramp resurfacing work

Crews will close the ramp from southbound 169 Highway to Richards Rd. beginning at 6am, Tuesday, September 28 and continuing until Wednesday, November 17 for grading, new drainage installation and ramp resurfacing work

Crews will close the ramp from northbound I-35 to eastbound I-70 from 9am until 3:30pm, Tuesday, September 28 for pipe inspection work

Crews will close the ramp from northbound I-35 to 6th from 9am until 3:30pm, Wednesday, 29 and again Thursday, September 30 for pipe inspection

 

This is all part of constructing a new Buck O’Neil Bridge that can be reasonably maintained, while providing a safe, connected and accessible transportation facility that improves system performance.   

 

The new Missouri River Bridge will cost close to $220 million dollars to construct and expected to be completed by 2024.

 

The current Buck O’Neil Memorial Bridge is a triple arch bridge carrying U.S. Route 169 over the Missouri River, and serves as a key regional connection between downtown Kansas City and communities north of the river. While safe, the bridge is nearing the end of its projected service life.

 

#BuckBridge

 

Motorists are reminded to slow down and pay attention while driving in work zones. Not all work zones look alike. Work zones can be moving operations, such as striping, patching or mowing. They can also be short term, temporary lane closures to make quick repairs or remove debris from the roadway.

 

For more information about MoDOT news, projects or events, please visit our website at www.modot.org/kansascity. For instant updates, follow MoDOT_KC on Twitter, or share posts and comments on our Facebook at www.facebook.com/MoDOT.KansasCity. MoDOT Kansas City maintains more than 7,000 miles of state roadway in nine counties. Sign up online for workzone updates or call 888-ASK-MODOT (275-6636).

 