Roundabout, Intersection Safety Improvements Project on Rt. 171 in Jasper Co. to Begin June 1

Jasper County – Drivers can expect occasional lane closures and traffic delays when a project to make intersection improvements along Missouri Route 171, including construction of a roundabout and resurfacing the highway, is scheduled to begin June 1, the Missouri Department of Transportation said.

Contractor crews will relocate the intersection at Missouri Route 171/Route 96 and Jasper County Route YY to the east and convert the intersection to a multi-lane roundabout. In addition, an approximately 26-mile stretch of Route 171 between the Missouri/Kansas state line and I-49 will be resurfaced.

The existing intersection is located immediately adjacent to the Kansas City Southern (KCS) railroad tracks which parallel Missouri Route 171. Vehicles, especially large semis and farm equipment, approaching from the west on Jasper County Route YY often must sit across the railroad tracks while waiting for a gap in traffic on Route 171. The project will increase the distance between the railroad tracks and Route 171, improving safety.

For much of the construction of the new intersection and roundabout, drivers will be able to travel along the existing roads. However, at times it will be necessary to close the roads. At those times, drivers will be directed to use signed detours along Missouri Route 43 and Jasper County Routes H, M and Z.

Weather and/or scheduling conflicts could alter the work schedule.

Project Information:

  • Prime contractor: APAC-Central Inc., Springfield
  • Total construction costs: $9.8 million
  • Contract completion date: December 15, 2021

 

 

(For more information, call MoDOT in Springfield at 417-895-7600 or visit www.modot.org/southwest)

(Follow MoDOT's Southwest District: Facebook | Twitter | Instagram |YouTube)

(Take the Challenge! Buckle Up/Phone Down)

Districts Involved
Southwest