Today (Monday), November 16
What: Drivers can expect delays and lane closings on I-44 at Mile Marker 103 in Marshfield
When: 9 a.m. until 3 p.m. Today (Monday), November 16, 2020
Traffic Impacts:
- East and westbound lane closings on I-44 at Mile Marker 103 in Marshfield
- One lane of traffic will be open at all times in the area where crews are working
- I-44 speed limit reduced to 60 mph
- Crews and equipment close to traffic in areas
- Motorists can expect significant traffic delays through the work zone
- Drivers urged to find alternate routes
- Electronic message boards located near the planned road work will alert drivers to any changes in the work scheduled
Why: Contractor crews will remove the temporary road striping and restripe I-44
(Weather or construction delays could alter the work schedule.)
Project Summary:
- Interchange:
- Build a new bridge to take Webster County Route CC over I-44 at Mile Marker 103
- Relocate Webster County Route CC at Rifle Range Road to intersect with I-44
- Build interchange ramps so drivers safely exit and enter I-44 at Webster County Route CC
- Build roundabouts at either end of interchange to connect with Brinkley Road/I-44 outer road on the west and Marshall Road/Route CC on the east
- Prime Contractor: H.R. Quadri Contractors, LLC of Van Buren
- Completion Date: June 2021. However, the interchange will be open to traffic by December 31, 2020.
- Total Project Cost: $16.4 million
- Sign up for project updates!
END
(For more information, call MoDOT in Springfield at 417-895-7600 or visit www.modot.org/southwest)
(Follow MoDOT's Southwest District: Facebook | Twitter | Instagram |YouTube)
(For timely traffic information in the Springfield area, visit www.ozarkstraffic.com)
(Take the Challenge! Buckle Up/Phone Down)
Districts Involved
Southwest
Published On