Week of October 19 - Route 160 Widening Willard to Springfield

UPCOMING TRAFFIC PATTERN CHANGES:

  • Traffic to one lane in each direction on Route 160 in the eastbound and westbound lanes
  • Farm Road 123 northeast of Route 160 OPEN
  • Frisco Highline Trail CLOSED at Hunt Road/Farm Road 103 until late October

Work Scheduled:  

  • Moving rock/dirt, laying base rock and paving to connect new pedestrian underpass to the Frisco Highline Trail
  • Paving to connect Farm Road 123 to Route 160 in new J-turn configuration
  • Paving new lanes of Route 160 between Farm Road 94 and Farm Road 123
  • Pouring concrete for islands, sidewalk and medians at Route 160 and Hunt Road/Farm Road 103 and Farm Road 94
  • Installing road signs in areas

Traffic Impacts:  

  • Frisco Highline Trail CLOSED at Hunt Road/Farm Road 103 until late October
  • New roundabouts OPEN on Route 160 at Jackson Street, Hunt Road/Farm Road 103, and Farm Road 94
  • Traffic to one lane in each direction on Route 160 in the eastbound and westbound lanes
  • Equipment crossing county farm roads at times. Short-term traffic stops by flaggers to allow equipment to cross the road.
  • Crews and equipment close to traffic
  • Crews may work Saturdays and Sundays to make up work missed due to weather/construction delays

(Weather or construction delays could alter the work schedule.)

Project Summary:

  • Widen Route 160 to four lanes between I-44 in Springfield and Jackson Street in Willard
  • Resurface the existing lanes of Route 160 between I-44 in Springfield and Route AB in Willard
  • Install concrete traffic barrier between lanes in areas
  • Add a pedestrian underpass underneath Route 160 at Hunt Road
  • Add a new box culvert to carry Frisco Highline Trail underneath Route 160 at Trail Mile 3
  • Add street lighting at intersections
  • Intersection improvements:
    • J-turn at Farm Road 123/Westgate Avenue
    • Right-in/Right-out at Haseltine Road (Farm Road 115)
    • Roundabout at Farm Road 94 near quarry
    • Add left-turn lane at Hughes Road
    • Roundabout at Farm Road 103/Melville Road/Hunt Road
    • Roundabout at Jackson Street
    • Add turn lanes at Greene County Route AB
  • Prime Contractor: APAC-Central, Springfield
  • Completion Date: December 1, 2020
  • Total Project Cost: $18.6 million 

END 



(For more information, call MoDOT in Springfield at 417-895-7600 or visit
www.modot.org/southwest



(Follow MoDOT's Southwest District:
Facebook | Twitter | Instagram |YouTube)



(For timely traffic information in the Springfield area, visit
www.ozarkstraffic.com) 

(Take the Challenge! Buckle Up/Phone Down)

Districts Involved
Southwest
MODOT Newsroom

The newsroom is a one-stop shop for media partners to find their local and statewide communications contacts and news releases, as well as download department leadership portraits and other media.

Visit the Newsroom
Real Time Traffic

Monitor real time traffic with our online traffic map.