TRAFFIC PATTERN CHANGES:
- Existing Route CC at Rifle Range Road CLOSED for tie ins to new Route CC
Work Scheduled:
- Interchange:
- Grading and hauling rock at Riffle Range Road for tie ins to new Route CC
- Pouring concrete for curb, sidewalk and truck apron at west roundabout along new Route CC
- Pouring concrete for bridge approaches and barrier wall of new Route CC bridge over I-44
- Installing street lighting at west roundabout of new Route CC
Traffic Impacts:
- Interchange:
- ROAD CLOSED: Existing Route CC at Rifle Range Road CLOSED until late-October
- Drivers urged to find alternate routes
- Nighttime lane closings on I-44 at Mile Marker 103 possible at times. Work hours: 8 p.m. to 6 a.m.
- Drivers should not pass in the work zone due to narrowed driving lanes on I-44 at Mile Marker 103
- I-44 speed limit reduced to 60 mph at times
- Crews and equipment close to traffic in areas
- ROAD CLOSED: Existing Route CC at Rifle Range Road CLOSED until late-October
- Roundabout: (Completed)
(Weather or construction delays could alter the work schedule.)
Project Summary:
- Interchange:
- Build a new bridge to take Webster County Route CC over I-44 at Mile Marker 103
- Relocate Webster County Route CC at Rifle Range Road to intersect with I-44
- Build interchange ramps so drivers safely exit and enter I-44 at Webster County Route CC
- Build roundabouts at either end of interchange to connect with Brinkley Road/I-44 outer road on the west and Marshall Road/Route CC on the east
- Prime Contractor: H.R. Quadri Contractors, LLC of Van Buren
- Completion Date: June 2021. However, the interchange will be open to traffic by December 31, 2020.
- Total Project Cost: $16.4 million
- Roundabout:
- Build a roundabout at the intersection of Hubble Drive, Buffalo Street and Banning Street
- Install new street lights at roundabout
- Resurface Hubble Drive between Rifle Range Road and Spur Drive (Route 38) in Marshfield
- Route CC between Rifle Range Road and Route 38 in Marshfield turned over to the city of Marshfield after completion of interchange project
- Prime Contractor: APAC-Central, Springfield
- Completion Date: December 2020
- Total Project Cost: $1.9 million
- Sign up for project updates!
END
(For more information, call MoDOT in Springfield at 417-895-7600 or visit www.modot.org/southwest)
(Follow MoDOT's Southwest District: Facebook | Twitter | Instagram |YouTube)
(For timely traffic information in the Springfield area, visit www.ozarkstraffic.com)
(Take the Challenge! Buckle Up/Phone)
Districts Involved
Southwest
Published On