TRAFFIC PATTERN CHANGES:
- Buffalo Street and Banning Street at Hubble Drive (Route CC) open to traffic as of Thursday, September 24
- Lane closings and possible delays on Route CC between Rifle Range Road and Ginger Road to install utility lines week of October 5
Work Scheduled:
- Interchange:
- Install utility lines at Route CC between Rifle Range Road and Ginger Road
- Grading and hauling rock for ditches and sidewalk at Route CC
- Pouring concrete for bridge approaches and barrier wall of new Route CC bridge over I-44
- Pouring concrete for curb and sidewalk at west roundabout and along new Route CC
- Installing street lighting at east and west roundabouts of new Route CC
- Striping east roundabout of new Route CC, Marshall Road and Route CC to Rifle Range Road
- Installing road signs
Traffic Impacts:
- Interchange:
- ROAD CLOSED: Marshall Road CLOSED between Ferndale Drive and Grayhawk Loop until mid-October
- Drivers urged to find alternate routes
- Lane closings and possible delays on Route CC at between Rifle Range Road and Ginger Road
- Drivers can expect flaggers directing them through the work zone
- Nighttime lane closings on I-44 at Mile Marker 103 possible at times. Work hours: 8 p.m. to 6 a.m.
- Drivers should not pass in the work zone due to narrowed driving lanes on I-44 at Mile Marker 103
- I-44 speed limit reduced to 60 mph at times
- Crews and equipment close to traffic in areas
- Roundabout:
- Buffalo Street and Banning Street at Hubble Drive (Route CC) open to traffic
- Hubble Drive (Route CC) OPEN to traffic in new roundabout configuration at Buffalo Street and Banning Street
(Weather or construction delays could alter the work schedule.)
Project Summary:
- Interchange:
- Build a new bridge to take Webster County Route CC over I-44 at Mile Marker 103
- Relocate Webster County Route CC at Rifle Range Road to intersect with I-44
- Build interchange ramps so drivers safely exit and enter I-44 at Webster County Route CC
- Build roundabouts at either end of interchange to connect with Brinkley Road/I-44 outer road on the west and Marshall Road/Route CC on the east
- Prime Contractor: H.R. Quadri Contractors, LLC of Van Buren
- Completion Date: June 2021. However, the interchange will be open to traffic by December 31, 2020.
- Total Project Cost: $16.4 million
- Roundabout:
- Build a roundabout at the intersection of Hubble Drive, Buffalo Street and Banning Street
- Install new street lights at roundabout
- Resurface Hubble Drive between Rifle Range Road and Spur Drive (Route 38) in Marshfield
- Route CC between Rifle Range Road and Route 38 in Marshfield turned over to the city of Marshfield after completion of interchange project
- Prime Contractor: APAC-Central, Springfield
- Completion Date: December 2020
- Total Project Cost: $1.9 million
- Sign up for project updates!
END
(For more information, call MoDOT in Springfield at 417-895-7600 or visit www.modot.org/southwest)
(Follow MoDOT's Southwest District: Facebook | Twitter | Instagram |YouTube)
(For timely traffic information in the Springfield area, visit www.ozarkstraffic.com)
(Take the Challenge! Buckle Up/Phone)
Districts Involved
Southwest
Published On