Update for Week of September 28 - Marshfield I-44 Interchange/Roundabout Projects

Work Scheduled:  

  • Interchange:
    • Grading and hauling rock at Marshall Road to connect to new roundabout and new Route CC
    • Grading and hauling rock east of Riffle Range Road to connect to new Route CC
    • Installing bridge deck (driving surface) of new Route CC bridge over I-44
    • Pouring concrete for curb, gutter and sidewalk along new Route CC
    • Installing street lighting at east and west roundabouts of new Route CC
    • Paving new Route CC at night
  • Roundabout:
    • Remove temporary road between Buffalo Street and Banning Street west of Hubble Drive (Route CC)
    • Striping Hubble Drive (Route CC), Buffalo Street south approach and Banning Street southeast approach
    • Installing road signs

 Traffic Impacts:  

  • Interchange:
    • ROAD CLOSED: Marshall Road CLOSED between Ferndale Drive and Grayhawk Loop until mid-October
    • Drivers urged to find alternate routes
    • Nighttime lane closings on I-44 at Mile Marker 103 possible at times. Work hours: 8 p.m. to 6 a.m.
    • Drivers should not pass in the work zone due to narrowed driving lanes on I-44 at Mile Marker 103
    • I-44 speed limit reduced to 60 mph at times
    • Crews and equipment close to traffic in areas
  • Roundabout:
    • CITY STREET CLOSED: Banning Street on the southeast side of Hubble Drive (Route CC) CLOSED until stop sign is installed
    • Signed detour in place
    • Drivers will have to use detour to get from Banning Streets to Hubble Drive
    • Crews and equipment close to traffic 

(Weather or construction delays could alter the work schedule.)

Project Summary:

  • Interchange:
    • Build a new bridge to take Webster County Route CC over I-44 at Mile Marker 103
    • Relocate Webster County Route CC at Rifle Range Road to intersect with I-44
    • Build interchange ramps so drivers safely exit and enter I-44 at Webster County Route CC
    • Build roundabouts at either end of interchange to connect with Brinkley Road/I-44 outer road on the west and Marshall Road/Route CC on the east
    • Prime Contractor: H.R. Quadri Contractors, LLC of Van Buren
    • Completion Date: June 2021. However, the interchange will be open to traffic by December 31, 2020.
    • Total Project Cost: $16.4 million
  • Roundabout:
    • Build a roundabout at the intersection of Hubble Drive, Buffalo Street and Banning Street
    • Install new street lights at roundabout
    • Resurface Hubble Drive between Rifle Range Road and Spur Drive (Route 38) in Marshfield
    • Route CC between Rifle Range Road and Route 38 in Marshfield turned over to the city of Marshfield after completion of interchange project
    • Prime Contractor: APAC-Central, Springfield
    • Completion Date: December 2020
    • Total Project Cost: $1.9 million
  • Sign up for project updates!

 END 

(For more information, call MoDOT in Springfield at 417-895-7600 or visit www.modot.org/southwest

(Follow MoDOT's Southwest District: Facebook | Twitter | Instagram |YouTube)

(For timely traffic information in the Springfield area, visit www.ozarkstraffic.com)

(Take the Challenge! Buckle Up/Phone)

Districts Involved
Southwest