Update for Week of August 17 - Route 160 Widening Willard to Springfield

UPCOMING TRAFFIC PATTERN CHANGES:

  • Greene County Farm Road 115 at U.S. Route 160 near Willard scheduled to OPEN Tuesday, August 18
  • Greene County Farm Road 94 at U.S. Route 160 in Willard scheduled to CLOSE Tuesday, August 18, for up to 30 days

Work Scheduled:  

  • Pouring concrete for curb and gutter at Route 160 and Farm Road 94 for new roundabout
  • Repairing concrete pavement on Route 160 between Greene County Route AB and Jackson Street
  • Grading and laying base rock for new highway lanes between Farm Road 115 and Farm Road 94
  • Moving rock/dirt in areas between Farm Road 94 and Farm Road 123

Traffic Impacts:  

  • ROAD CLOSING: Farm Road 94 at Route 160 scheduled to CLOSE Tuesday, August 18, for up to 30 days to build new roundabout
  • Farm Road 115 at Route 160 scheduled to OPEN Tuesday, August 18
  • New roundabout at Route 160 and Jackson Street open to traffic
  • New roundabout at Route 160 and Hunt Road/Route 160 open in single-lane configuration
  • One-lane traffic with flaggers directing drivers through the work zone on Route 160 between Route AB and Jackson Street for pavement repairs. Work hours: 9 a.m. to 3 p.m. Monday-Friday
  • Short-term traffic stops on Route 160 near Hunt Road/Farm Road 103 to allow equipment to cross the road
  • Equipment crossing county farm roads at times. Short-term traffic stops by flaggers to allow equipment to cross the road.
  • Crews and equipment close to traffic
  • Crews may work Saturdays and Sundays to make up work missed due to weather/construction delays

(Weather or construction delays could alter the work schedule.)

Project Summary:

  • Widen Route 160 to four lanes between I-44 in Springfield and Jackson Street in Willard
  • Resurface the existing lanes of Route 160 between I-44 in Springfield and Route AB in Willard
  • Install concrete traffic barrier between lanes in areas
  • Add a pedestrian underpass underneath Route 160 at Hunt Road
  • Add a new box culvert to carry Frisco Highline Trail underneath Route 160 at Trail Mile 3
  • Add street lighting at intersections
  • Intersection improvements:
    • J-turn at Farm Road 123/Westgate Avenue
    • Right-in/Right-out at Haseltine Road (Farm Road 115)
    • Roundabout at Farm Road 94 near quarry
    • Add left-turn lane at Hughes Road
    • Roundabout at Farm Road 103/Melville Road/Hunt Road
    • Roundabout at Jackson Street
    • Add turn lanes at Greene County Route AB
  • Prime Contractor: APAC-Central, Springfield
  • Completion Date: December 1, 2020
  • Total Project Cost: $18.6 million 

END 



(For more information, call MoDOT in Springfield at 417-895-7600 or visit
www.modot.org/southwest



(Follow MoDOT's Southwest District:
Facebook | Twitter | Instagram |YouTube)



(For timely traffic information in the Springfield area, visit
www.ozarkstraffic.com) 

(Take the Challenge! Buckle Up/Phone Down)

Districts Involved
Southwest
MODOT Newsroom

The newsroom is a one-stop shop for media partners to find their local and statewide communications contacts and news releases, as well as download department leadership portraits and other media.

Visit the Newsroom
Real Time Traffic

Monitor real time traffic with our online traffic map.