In Marshfield on August 4 & 5 for Bridge Work
What: I-44 traffic slowed and possibly stopped near Mile Marker 103 in Marshfield
When/Where:
- 10 p.m. – 6 a.m. Tuesday, August 4, eastbound lanes of I-44 at Mile Marker 103
- 10 p.m. – 6 a.m. Wednesday, August 5, westbound lanes of I-44 at Mile Marker 103
Why: Construction crews installing and securing bridge girders as part of the I-44 Interchange Project in Marshfield
Traffic Impacts:
- Law enforcement officers slowing and stopping traffic on I-44 for up to 15 minutes at night while contractor crews lift bridge girders into place and secure them
- Drivers urged to avoid the area during the work, if possible
- Electronic message boards located near the planned road work will alert drivers to any changes in the work scheduled
(Weather or construction delays could alter the work schedule.)
Project Summary:
- Build a new bridge to take Webster County Route CC over I-44 at Mile Marker 103
- Relocate Webster County Route CC at Rifle Range Road to intersect with I-44
- Build interchange ramps so drivers safely exit and enter I-44 at Webster County Route CC
- Build roundabouts at either end of interchange to connect with Brinkley Road/I-44 outer road on the west and Marshall Road/Route CC on the east
- Prime Contractor: H.R. Quadri Contractors, LLC of Van Buren
- Completion Date: June 2021. However, the interchange will be open to traffic by December 31, 2020.
- Total Project Cost: $16.4 million
- Sign up for project updates!
END
(For more information, call MoDOT in Springfield at 417-895-7600 or visit www.modot.org/southwest)
(Follow MoDOT's Southwest District: Facebook | Twitter | Instagram |YouTube)
(For timely traffic information in the Springfield area, visit www.ozarkstraffic.com)
(Take the Challenge! Buckle Up/Phone Down)
Districts Involved
Southwest
Published On