Update for Week of August 3 - Route 160 Widening Willard to Springfield

UPCOMING TRAFFIC PATTERN CHANGES:

  • New roundabout at U.S. Route 160 and Jackson Street scheduled to OPEN to traffic in early August
  • Farm Road 94 at Route 160 scheduled to CLOSED at Route 160 the week of August 10 for up to 30 days

Work Scheduled: 

  • Pouring concrete for curb and gutter at Route 160 and Jackson Street for new roundabout
  • Installing permanent signals at Route 160 and Greene County Route AB
  • Grading and laying base rock for new highway lanes between Farm Road 115 and Farm Road 94
  • Moving rock/dirt in areas between Farm Road 115 and Farm Road 123
  • Installing street lights at Route 160 and Farm Road 94

Traffic Impacts:  

  • EARLY HEADS UP:
    • New roundabout at Route 160 and Jackson Street scheduled to OPEN as a single lane roundabout early August
    • Farm Road 94 at Route 160 scheduled to CLOSED the week of August 10 for up to 30 days to begin construction of new roundabout
  • DELAYS EXPECTED:
    • Short-term traffic stops on Route 160 near Hunt Road/Farm Road 103 to allow equipment to cross the road
  • TRAFFIC SHIFT on Route 160
    • Hunt Road:
      • Traffic shifted to the west
      • Crews and equipment close to traffic on east side of Route 160
    • Traffic shifted to new lanes of Route 160 between Hunt Road and Jackson Street to allow crews to pavement repairs to existing roadway
  • Equipment crossing county farm roads at times. Short-term traffic stops by flaggers to allow equipment to cross the road.
  • Crews and equipment close to traffic
  • Crews may work Saturdays and Sundays to make up work missed due to weather/construction delays

Project Summary:

  • Widen Route 160 to four lanes between I-44 in Springfield and Jackson Street in Willard
  • Resurface the existing lanes of Route 160 between I-44 in Springfield and Route AB in Willard
  • Install concrete traffic barrier between lanes in areas
  • Add a pedestrian underpass underneath Route 160 at Hunt Road
  • Add a new box culvert to carry Frisco Highline Trail underneath Route 160 at Trail Mile 3
  • Add street lighting at intersections
  • Intersection improvements:
    • J-turn at Farm Road 123/Westgate Avenue
    • Right-in/Right-out at Haseltine Road (Farm Road 115)
    • Roundabout at Farm Road 94 near quarry
    • Add left-turn lane at Hughes Road
    • Roundabout at Farm Road 103/Melville Road/Hunt Road
    • Roundabout at Jackson Street
    • Add turn lanes at Greene County Route AB
  • Prime Contractor: APAC-Central, Springfield
  • Completion Date: December 1, 2020
  • Total Project Cost: $18.6 million 

END 



(For more information, call MoDOT in Springfield at 417-895-7600 or visit
www.modot.org/southwest



(Follow MoDOT's Southwest District:
Facebook | Twitter | Instagram |YouTube)



(For timely traffic information in the Springfield area, visit
www.ozarkstraffic.com) 

(Take the Challenge! Buckle Up/Phone Down)

Districts Involved
Southwest