- Hubble Driver (Route CC) schedule to CLOSE at Banning/Buffalo Streets in Marshfield for construction of new pavement at roundabout
Work Scheduled:
- Interchange:
- Grading and hauling rock/dirt to build up areas on the south side of I-44 for bridge ends
- Installing retaining walls on either side of I-44 for new interchange bridge
- Installing storm drain pipes in areas
- Roundabout:
- Grading and hauling rock/dirt on Route CC
- Installing storm drain pipe on Route CC
- Paving roundabout
- Installing road signs for roundabout
Traffic Impacts:
- Interchange:
- ROAD CLOSED: Brinkley Road (I-44 north outer road) CLOSED east of Webster County Route W
- Signed detour: Webster County Route W, Vinyard Road and Rusty Road
- Brinkley Road closed until fall 2020
- Nighttime lane closings on I-44 at Mile Marker 103 possible at times. Work hours: 7 p.m. to 6 a.m.
- Drivers should not pass in the work zone due to narrowed driving lanes on I-44 at Mile Marker 103
- I-44 speed limit reduced to 60 mph at times
- Crews and equipment close to traffic in areas
- ROAD CLOSED: Brinkley Road (I-44 north outer road) CLOSED east of Webster County Route W
- Roundabout:
- Hubble Drive (Route CC) CLOSED:
- Hubble Drive CLOSED between Elm Street and Missouri Route 38 (Jackson Street) for up to 6 days starting July 20
- Signed detours in place using Jackson Street and Elm Street along with other city streets
- Drivers will be able to get to driveways and entrances on either side of the roundabout, but will not be able to travel through the Hubble Drive closure at Banning/Buffalo Streets
- CITY STREETS CLOSED: Buffalo Street on the north side and Banning Street on the west side of Hubble Drive (Route CC) CLOSED for several months
- Signed detours in place
- Drivers will have to use detour to get from Buffalo and Banning Streets to Hubble Drive
- Crews and equipment close to traffic
(Weather or construction delays could alter the work schedule.)
Project Summary:
- Interchange:
- Build a new bridge to take Webster County Route CC over I-44 at Mile Marker 103
- Relocate Webster County Route CC at Rifle Range Road to intersect with I-44
- Build interchange ramps so drivers safely exit and enter I-44 at Webster County Route CC
- Build roundabouts at either end of interchange to connect with Brinkley Road/I-44 outer road on the west and Marshall Road/Route CC on the east
- Prime Contractor: H.R. Quadri Contractors, LLC of Van Buren
- Completion Date: June 2021. However, the interchange will be open to traffic by December 31, 2020.
- Total Project Cost: $16.4 million
- Roundabout:
- Build a roundabout at the intersection of Hubble Drive, Buffalo Street and Banning Street
- Install new street lights at roundabout
- Resurface Hubble Drive between Rifle Range Road and Spur Drive (Route 38) in Marshfield
- Route CC between Rifle Range Road and Route 38 in Marshfield turned over to the city of Marshfield after completion of interchange project
- Prime Contractor: APAC-Central, Springfield
- Completion Date: December 2020
- Total Project Cost: $1.9 million
- Sign up for project updates!
END
(For more information, call MoDOT in Springfield at 417-895-7600 or visit www.modot.org/southwest)
(Follow MoDOT's Southwest District: Facebook | Twitter | Instagram |YouTube)