Update for Week of July 13 - Route 160 Widening Willard to Springfield

UPCOMING TRAFFIC PATTERN CHANGES:

  • Northeast section of the new roundabout at Route 160 and Hunt Road/Farm Road 103 open to traffic during the week

Work Scheduled: 

  • Building new roundabout at Route 160 and Jackson Street
  • Paving southwest portion of new roundabout at Hunt Road/Farm Road 103 at night
  • Paving new lanes of Route 160 between Hunt Road and Jackson Street
  • Grading and laying base rock for new highway lanes near Jackson Street
  • Blasting and moving rock/dirt in areas between Farm Road 115 and Farm Road 123

Traffic Impacts:  

  • ROADS CLOSING:
    • Hunt Road CLOSED southwest of Route 160 until mid-July
    • Jackson Street CLOSED north of Route 160 until late July to mid-August
  • DELAYS EXPECTED:
    • Short-term traffic stops on Route 160 near Hunt Road/Farm Road 103 to allow equipment to cross the road
    • Flaggers will stop traffic on Route 160 during nighttime hours at Hunt Road/Farm Road 103
  • TRAFFIC STOPS for rock blasting:  
    • Route 160 traffic stopped for up to 15 minutes between 9 a.m. and 5 p.m. Monday-Friday
    • Traffic also may be stopped on nearby county farm roads
    • Flaggers will stop traffic
    • Blasting is nearing completion
  • TRAFFIC SHIFT on Route 160 at Hunt Road:
    • Traffic shifted to the west
    • Northbound-to-westbound turn lane Closed
    • Crews and equipment close to traffic on east side of Route 160
  • EARLY HEADS UP: Northeast section of the new roundabout at Route 160 and Hunt Road/Farm Road 103 scheduled to open during the week
  • Equipment crossing county farm roads at times. Short-term traffic stops by flaggers to allow equipment to cross the road.
  • Crews and equipment close to traffic
  • Crews may work Saturdays and Sundays to make up work missed due to weather/construction delays

(Weather or construction delays could alter the work schedule.) 

Project Summary:

  • Widen Route 160 to four lanes between I-44 in Springfield and Jackson Street in Willard
  • Resurface the existing lanes of Route 160 between I-44 in Springfield and Route AB in Willard
  • Install concrete traffic barrier between lanes in areas
  • Add a pedestrian underpass underneath Route 160 at Hunt Road
  • Add a new box culvert to carry Frisco Highline Trail underneath Route 160 at Trail Mile 3
  • Add street lighting at intersections
  • Intersection improvements:
    • J-turn at Farm Road 123/Westgate Avenue
    • Right-in/Right-out at Haseltine Road (Farm Road 115)
    • Roundabout at Farm Road 94 near quarry
    • Add left-turn lane at Hughes Road
    • Roundabout at Farm Road 103/Melville Road/Hunt Road
    • Roundabout at Jackson Street
    • Add turn lanes at Greene County Route AB
  • Prime Contractor: APAC-Central, Springfield
  • Completion Date: December 1, 2020
  • Total Project Cost: $18.6 million 

END 



(For more information, call MoDOT in Springfield at 417-895-7600 or visit
www.modot.org/southwest



(Follow MoDOT's Southwest District:
Facebook | Twitter | Instagram |YouTube)



(For timely traffic information in the Springfield area, visit
www.ozarkstraffic.com) 

(Take the Challenge! Buckle Up/Phone Down)

Districts Involved
Southwest
MODOT Newsroom

The newsroom is a one-stop shop for media partners to find their local and statewide communications contacts and news releases, as well as download department leadership portraits and other media.

Visit the Newsroom
Real Time Traffic

Monitor real time traffic with our online traffic map.