What: New Missouri Route 37 bridge over Center Creek OPEN to traffic north of Sarcoxie
When: 12:30 p.m., Tuesday, June 30
Details: Contractor crews finished work to build new Route 37 bridge over Center Creek
Project Details:
- Replace Route 37 bridge and upgrade guardrail over Center Creek with new 15 feet longer, 10 feet wider and one foot higher bridge
- Total project cost: $2.1 million
- The bridge was originally closed in January 2020
- Original completion date: September 1, 2020
- Prime contractor: Hartman & Company, Springfield
(For more information, call MoDOT in Springfield at 417-895-7600 or visit www.modot.org/southwest)