Update for Week of July 6 - Marshfield I-44 Interchange/Roundabout Projects

Work Scheduled:  

  • Interchange:
    • Grading and hauling rock/dirt to build up areas on the south side of I-44 for bridge ends
    • Installing retaining walls on either side of I-44 for new interchange bridge
    • Installing storm drain pipes in areas
  • Roundabout:
    • Grading rock and dirt on north side of Hubble Drive (Route CC) to build north half of roundabout
    • Laying base rock for future driving lanes of roundabout
    • Pouring concrete for curbs and shoulders for roundabout
    • Installing storm drain pipe east of Banning Street
    • Installing street lighting for roundabout

Traffic Impacts:  

  • Interchange:
    • ROAD CLOSED: Brinkley Road (I-44 north outer road) CLOSED east of Webster County Route W
      • Signed detour: Webster County Route W, Vinyard Road and Rusty Road
      • Brinkley Road closed until fall 2020
    • Nighttime lane closings on I-44 at Mile Marker 103 possible at times. Work hours: 7 p.m. to 6 a.m.
    • Drivers should not pass in the work zone due to narrowed driving lanes on I-44 at Mile Marker 103
    • I-44 speed limit reduced to 60 mph at times
    • Crews and equipment close to traffic in areas
  • Roundabout:
    • ROADS CLOSED: Buffalo Street on the north side and Banning Street on the west side of Hubble Drive (Route CC) CLOSED for several months
      • Signed detours in place
      • Drivers will have to use detour to get from Buffalo and Banning Streets to Hubble Drive
      • Crews and equipment close to traffic 

(Weather or construction delays could alter the work schedule.)

Project Summary:

  • Interchange:
    • Build a new bridge to take Webster County Route CC over I-44 at Mile Marker 103
    • Relocate Webster County Route CC at Rifle Range Road to intersect with I-44
    • Build interchange ramps so drivers safely exit and enter I-44 at Webster County Route CC
    • Build roundabouts at either end of interchange to connect with Brinkley Road/I-44 outer road on the west and Marshall Road/Route CC on the east
    • Prime Contractor: H.R. Quadri Contractors, LLC of Van Buren
    • Completion Date: June 2021. However, the interchange will be open to traffic by December 31, 2020.
    • Total Project Cost: $16.4 million
  • Roundabout:
    • Build a roundabout at the intersection of Hubble Drive, Buffalo Street and Banning Street
    • Install new street lights at roundabout
    • Resurface Hubble Drive between Rifle Range Road and Spur Drive (Route 38) in Marshfield
    • Route CC between Rifle Range Road and Route 38 in Marshfield turned over to the city of Marshfield after completion of interchange project
    • Prime Contractor: APAC-Central, Springfield
    • Completion Date: December 2020
    • Total Project Cost: $1.9 million
  • Sign up for project updates!

 END 

(For more information, call MoDOT in Springfield at 417-895-7600 or visit www.modot.org/southwest

(Follow MoDOT's Southwest District: Facebook | Twitter | Instagram |YouTube)

(For timely traffic information in the Springfield area, visit www.ozarkstraffic.com)

(Take the Challenge! Buckle Up/Phone Down)

Districts Involved