Update for Week of June 1 - Marshfield I-44 Interchange/Roundabout Projects

Work Scheduled:  

  • Interchange:
    • Grading and hauling rock/dirt to build up areas on the south side of I-44 for bridge ends
    • Installing drain pipes on the north side of I-44
    • Building box culvert for Elm Street extension
    • The week of June 8, installing retaining walls on either side of I-44 for new interchange bridge
  • Roundabout:
    • Grading rock and dirt on north side of Hubble Drive (Route CC) to build north half of roundabout
    • Installing work zone/detour signs 

Traffic Impacts:  

  • Interchange:
    • ROAD CLOSED: Brinkley Road (I-44 north outer road) CLOSED east of Webster County Route W
      • Signed detour: Webster County Route W, Vinyard Road and Rusty Road
      • Brinkley Road closed until fall 2020
    • Nighttime lane closings on I-44 at Mile Marker 103 possible at times. Work hours: 7 p.m. to 6 a.m.
    • I-44 speed limit reduced to 60 mph at times
    • Crews and equipment close to traffic in areas
  • Roundabout:
    • ROADS CLOSED: Buffalo Street on the north side and Banning Street on the east side of Hubble Drive (Route CC) CLOSED for several months
      • Signed detours in place
      • Drivers will have to use detour to get from Buffalo and Banning Streets to Hubble Drive
      • Crews and equipment close to traffic 

(Weather or construction delays could alter the work schedule.) 

Project Summary:

  • Interchange:
    • Build a new bridge to take Webster County Route CC over I-44 at Mile Marker 103
    • Relocate Webster County Route CC at Rifle Range Road to intersect with I-44
    • Build interchange ramps so drivers safely exit and enter I-44 at Webster County Route CC
    • Build roundabouts at either end of interchange to connect with Brinkley Road/I-44 outer road on the west and Marshall Road/Route CC on the east
    • Prime Contractor: H.R. Quadri Contractors, LLC of Van Buren
    • Completion Date: June 2021. However, the interchange will be open to traffic by December 31, 2020.
    • Total Project Cost: $16.4 million
  • Roundabout:
    • Build a roundabout at the intersection of Hubble Drive, Buffalo Street and Banning Street
    • Install new street lights at roundabout
    • Resurface Hubble Drive between Rifle Range Road and Spur Drive (Route 38) in Marshfield
    • Route CC between Rifle Range Road and Route 38 in Marshfield turned over to the city of Marshfield after completion of interchange project
    • Prime Contractor: APAC-Central, Springfield
    • Completion Date: December 2020
    • Total Project Cost: $1.9 million
  • Sign up for project updates!

 

END 

(For more information, call MoDOT in Springfield at 417-895-7600 or visit
www.modot.org/southwest

(Follow MoDOT's Southwest District:
Facebook | Twitter | Instagram |YouTube)

(For timely traffic information in the Springfield area, visit
www.ozarkstraffic.com) 

(Take the Challenge! Buckle Up/Phone Down)

 

Districts Involved
Southwest
MODOT Newsroom

The newsroom is a one-stop shop for media partners to find their local and statewide communications contacts and news releases, as well as download department leadership portraits and other media.

Visit the Newsroom
Real Time Traffic

Monitor real time traffic with our online traffic map.