Route 160 Widening: Update for Week of March 9

U.S. Route 160 Widening Project - Willard to Springfield
  • TRAFFIC STOPS of up to 15 minutes on Route 160 for blasting one time per day between 10 a.m. and 2 p.m. Monday-Friday
  • TRAFFIC SHIFT on Route 160 at Hunt Road for construction of pedestrian underpass 

Work Scheduled:  

  • Blasting rock in areas between Farm Road 94 and Farm Road 123
  • Installing pedestrian underpass underneath Route 160 south of Hunt Road
  • Hauling rock to various locations on the project
  • Installing drain pipes in various locations 

Traffic Impacts:  

  • TRAFFIC SHIFT on Route 160 at Hunt Road:
    • Traffic shifted to the west
    • Northbound-to-westbound turn lane shortened
    • Crews and equipment close to traffic on east side of Route 160
  • TRAFFIC STOPS for rock blasting:  
    • Route 160 traffic stopped for up to 15 minutes once a day at some point between 10 a.m. and 2 p.m. Monday-Friday
    • Traffic also may be stopped on nearby county farm roads
    • Flaggers will stop traffic
    • Rock blasting could take several months to complete
  • Equipment crossing county farm roads at times. Short-term traffic stops by flaggers to allow equipment to cross the road.
  • Route 160 shoulder closed in areas at times
  • Crews and equipment close to traffic
  • Equipment entering and leaving work areas
  • Crews may work Saturdays and Sundays to make up work missed due to weather/construction delays 

(Weather or construction delays could alter the work schedule.) 

Project Summary:

  • Widen Route 160 to four lanes between I-44 in Springfield and Jackson Street in Willard
  • Resurface the existing lanes of Route 160 between I-44 in Springfield and Route AB in Willard
  • Install concrete traffic barrier between lanes in areas
  • Add a pedestrian underpass underneath Route 160 at Hunt Road
  • Add a new box culvert to carry Frisco Highline Trail underneath Route 160 at Trail Mile 3
  • Add street lighting at intersections
  • Intersection improvements:
    • J-turn at Farm Road 123/Westgate Avenue
    • Right-in/Right-out at Haseltine Road (Farm Road 115)
    • Roundabout at Farm Road 94 near quarry
    • Add left-turn lane at Hughes Road
    • Roundabout at Farm Road 103/Melville Road/Hunt Road
    • Roundabout at Jackson Street
    • Add turn lanes at Greene County Route AB
  • Prime Contractor: APAC-Central, Springfield
  • Completion Date: December 1, 2020
  • Total Project Cost: $18.6 million 

END 



(For more information, call MoDOT in Springfield at 417-895-7600 or visit
www.modot.org/southwest



(Follow MoDOT's Southwest District:
Facebook | Twitter | Instagram |YouTube)



(For timely traffic information in the Springfield area, visit
www.ozarkstraffic.com) 

(Take the Challenge! Buckle Up/Phone Down)

 

Districts Involved
Southwest
MODOT Newsroom

The newsroom is a one-stop shop for media partners to find their local and statewide communications contacts and news releases, as well as download department leadership portraits and other media.

Visit the Newsroom
Real Time Traffic

Monitor real time traffic with our online traffic map.