Update for Week of September 18-25
- TRAFFIC ALERT: Southbound Route 65-to-westbound Route 60 ramp CLOSED on Thursday night, Sept. 19, for shoulder paving
Work Scheduled:
- Diamond-grind (smooth) new Route 65 pavement between Route 60 and Sunshine Street. (Northbound during week of Sept. 16 and southbound week of Sept. 23)
- Install guardrail in areas along Route 65
- Pave shoulders in areas along Route 65
- Apply seed and mulch to southbound Route 65 shoulder north of Route 60
Traffic Impacts:
- ALL Route 65 lanes open during daytime hours
- RAMP CLOSING: Southbound Route 65-to-westbound Route 60 ramp closed for shoulder paving. Work hours: 10 p.m. to 6 a.m. Thursday, September 19.
- NIGHT WORK: One or two lanes of northbound or southbound Route 65 between Route 60 and Sunshine Street closed. One lane in each direction will remain open. Work hours: 8 p.m. to 6 a.m. Monday-Friday.
- Temporary traffic signals on flash at Blackman Road/Battlefield Road and Greene County Route D/Route 125 intersections. Signals removed during week of Sept. 16.
(Weather or construction delays could alter the work schedule.)
Project Summary:
- Sunday-Thursday, August 4-8 -- COMPLETE
- All southbound lanes of Route 65 CLOSED between Sunshine Street and Battlefield Road
- Southbound on ramp from Sunshine Street to Route 65 CLOSED
- Southbound off ramp from Route 65 to Battlefield Road CLOSED
- Thursday-Friday, August 8-16 -- COMPLETE
- All southbound lanes of Route 65 CLOSED between Battlefield Road and Route 60
- Southbound Route 65 OPEN between Sunshine Street and Battlefield Road, but reduced to one lane
- Southbound on ramp from Battlefield Road to Route 65 CLOSED
- Southbound Route 65-to-westbound Route 60 ramp CLOSED
All lanes of Route 65 open during the Labor Day holiday (Friday-Friday, August 16-September 6)
- Friday-Friday, September 6-14 -- COMPLETE
- All northbound lanes of Route 65 CLOSED between Route 60 and Sunshine Street
- Eastbound Route 60-to-northbound Route 65 ramp CLOSED
- Westbound Route 60-to-northbound Route 65 ramp CLOSED
- Northbound off ramp from Route 65 to Battlefield Road CLOSED
- Northbound on ramp from Battlefield Road to northbound Route 65 CLOSED
- Northbound off ramp from Route 65 to Sunshine Street CLOSED
- Eastbound on ramp from Glenstone Avenue to Route 60 CLOSED
- Route 60 crossovers CLOSED between Route 65 and Greene County Routes NN/J
- September 16-November 1
- Nighttime lane closings for shoulder construction/guardrail/striping/pavement smoothing
- Prime Contractor: Emery Sapp and Sons, Inc. of Columbia
- Completion Date: November 2019 (However, contractor plans to complete project by late September.)
- Total Project Cost: $8.1 million
END
(For more information, call MoDOT in Springfield at 417-895-7600 or visit www.modot.org/southwest)
(Follow MoDOT's Southwest District: Facebook | Twitter | Instagram |YouTube)
(For timely traffic information in the Springfield area, visit www.ozarkstraffic.com)
(Take the Challenge! Buckle Up/Phone Down)