The following is a listing of general highway maintenance and construction work in the mid-Missouri area for the two-week period of September 2– September 13, 2019. The projects listed will include lane closures that could cause traffic delays. Full roadway closures are also noted. Weather conditions may postpone the work schedule.
MoDOT reminds motorists to buckle up, slow down, follow posted signs and drive safely through work areas. For more information about a project, please contact MoDOT at 1-888-ASK-MoDOT (275-6636) or visit www.modot.org/modot-central-district. You can also follow MoDOT’s Central Missouri District on Twitter and Facebook at https://twitter.com/MoDOT_Centraland MoDOT Central Missouri District.
All Counties
Daylight Hours
Mowing, striping, brush cutting and guardrail repair continues in various locations. Motorists should travel with care and be alert to slow-moving equipment along the road.
Boone County
Daylight/Overnight Hours
Route 63 over Gans Creek, south of Discovery Parkway – Bridge rehabilitation in the northbound lanes is scheduled to begin the week of September 9.
Route 63 over the Katy Trail, south Claysville Road – Bridge rehabilitation in the northbound lanes is scheduled to begin the week of September 9.
Route 63 between Route 763 and the Randolph County line – Paving will take place the week of September 2.
Daylight Hours
Route 163 between Route H and Route K – Shoulder widening continues. Installation of rumble strips and pavement markings will take place the week of September 2. The project is scheduled for completion in November.
Route 163 (Providence Road) between Interstate 70 and Route K – Signal upgrades, sidewalk repair and ADA improvements in various locations continue. The project is scheduled for completion in August, 2020.
Route 763 (College Avenue) between Route 740 (Stadium Boulevard) and Business Loop 70 – Signal upgrades, sidewalk repair and ADA improvements in various locations continue. The project is scheduled for completion in November.
Route Y between Route M and Route J in Callaway County – Shoulder widening continues. Installation of rumble strips and pavement markings will take place the week of September 2. The project is scheduled for completion in November.
Callaway County
Daylight Hours
Route O between Route D and State Street – Resurfacing, shoulder additions and ADA improvements continue. The project is scheduled for completion in November.
Route Y between Route J and Route M in Boone County – Shoulder widening continues. Installation of rumble strips and pavement markings will take place the week of September 2. The project is scheduled for completion in November.
Route AA between Route 54 and Route 94 – Culvert pipe replacement will take place Tuesday, September 3 through Thursday, September 5.
Camden County
Daylight/Overnight Hours
Route 5 between Route 54 and Pier Thirty-One Road – Roadside maintenance continues. The project is scheduled for in late September.
Route 54 between Jeffries Road and Passover Road – Shoulder repair will take place in the eastbound lanes Tuesday, September 3 through Thursday, September 5.
Route H between Business Route 54 and Route J – Roadway patching will take place between Tuesday, September 3 and Thursday, September 12.
Route N between Route 54 and Bannister Hollow Road – Culvert pipe replacement will take place Tuesday, September 3 through Thursday, September 12.
Route HH between Interstate 70 and Route 54 – Roadway patching will take place between Tuesday, September 3 and Thursday, September 12.
Route KK between Osage Beach Parkway and Turkey Bend Road – Sidewalk improvements and signal installation is scheduled in mid-September.
Cole County
Daylight Hours
Route 63 between Route 50 and Route 28 in Maries County – Concrete repair continues. The project is scheduled for completion in November.
Route C between Route 54 and Route 52 in Morgan County – Guardrail installation, milling and resurfacing continues. The project is scheduled for completion in November.
Cooper County
Overnight Hours/Daylight Hours
Route 87 between Route 5 and Route O in Moniteau County – Microsurfacing continues. The project is scheduled for completion in late September.
Route H between Route O and Route 50 in Moniteau County – Pavement repair will take place Monday, September 9 through Thursday, September 12.
Crawford County
Daylight Hours
Route 19 between Interstate 44 Outer Road and Main Street – ADA improvements continue. The project is scheduled for completion in December.
Route 19 between Route O and Route P – Pavement marking will take place Tuesday, September 3 through Thursday, September 5.
Route 19 between Grand Drive and the Gasconade County line – Microsurfacing and shoulder widening continues. The project is scheduled for completion in October.
Route H between Interstate 44 and Cave Road – Edge rut repair will take place Tuesday, September 3 through Thursday, September 5.
Gasconade County
Daylight/Overnight Hours
Route T over Bourbeuse River – New bridge construction continues. The bridge is closed until December.
Howard County
Daylight/Overnight Hours
Route 87 between Route 5 and Route 40 – Paving operations continues the week of September 2. The project is scheduled for completion in November.
Daylight Hours
Route 40 between Route 5 and County Road 441 – Milling drive surface will take place Tuesday, September 3 through Thursday, September 5.
Route 240 between Route 40 and Depot Street – Patching drive surface will take place Tuesday, September 3 through Thursday, September 12.
Laclede County
Overnight Hours
Interstate 44 between mile marker 113 and mile marker 145 – Concrete repairs in the westbound and eastbound lanes at various locations will begin the week of September 2.
Daylight/ Overnight Hours
Interstate 44 Outer Road over the Gasconade River, west of Route 133 –Bridge replacement is complete. Occasional lane closures are possible for cleanup work.
Maries County
Daylight Hours
Route 63 between Route 28 and Route 50 in Cole County – Concrete repair continues. The project is scheduled for completion in November.
Route 68 over Lanes Fork Creek, east of County Road 444 – Bridge maintenance will take place Tuesday, September 3 through Thursday September 5.
Route 68 over Coppedge Creek, east of Route H – Bridge maintenance will take place Tuesday, September 3 through Thursday September 5.
Miller County
Daylight Hours
Route EE between Route 17 and Route U – Pavement repair will take place Tuesday, September 3 through Thursday, September 12.
Moniteau County
Daylight Hours
Route 87 between Route O and Route 5 in Cooper County – Microsurfacing continues. The project is scheduled for completion in September.
Route C between Route 54 in Cole County and Route 52 in Morgan County – Guardrail installation, milling and resurfacing continues. The project is scheduled for completion in November.
Route H between Route 50 and Route O in Cooper County – Pavement repair will take place Monday, September 9 through Thursday, September 12.
Morgan County
Daylight Hours
Route C between Route 52 and Route 54 in Cole County – Guardrail installation, milling and resurfacing continues. The project is scheduled for completion in November.
Route JJ and Route 135 and Route D – Pavement repair will take place Tuesday, September 3 through Thursday, September 5.
Osage County
Daylight Hours
Route 63 between Route 50 in Cole County and Route 28 in Maries County – Concrete repair continues. The project is scheduled for completion in November.
Route C between Route 100 and Route A – Chip sealing and guardrail installation is underway. The project is scheduled for completion in October.
Route P between Route 63 and Route 133 – Culvert pipe replacement will take place Tuesday, September 2 through Friday, September 13.
Route T between Route 63 and Route AA – Culvert pipe replacement will take place Tuesday, September 2 through Friday, September 13.
Route W between Route 50 to Route A – Chip sealing and guardrail installation continues. The project is scheduled for completion in October.
Phelps County
Overnight Hours
Route 63 between Interstate 44 and Route CC – Roadway resurfacing and sidewalk repair continues. The project is scheduled for completion in October.
Daylight Hours
Route 68 between Route 8 and Route JJ – Pavement patching will take place Tuesday, September 3 through Thursday, September 12.
Route C between Interstate 44 and County Road 8490 – Pavement patching will take place Tuesday, September 3 and Thursday, September 12.
Route W between Route 63 and Route 7220 – Pavement patching will take place Tuesday, September 3 and Thursday, September 12.
Route AA between Route P and County Road 7640 – Pavement patching will take place Tuesday, September 3 through Thursday, September 12.
Route BB between County Road 3220 and County Road 3410 – Culvert pipe replacement continues. The road will be closed at each culvert pipe replacement area.
Pulaski County
Daylight/Overnight Hours
Interstate 44 at mile marker 159 – Concrete repair will take place in the westbound lanes Sunday, September 8.
Route H between Route 17 and the end of state maintenance – Roadway resurfacing continues. The project is scheduled for completion in November.
Route Y over Interstate 44 – Concrete repair will take place in the westbound lanes Tuesday, September 10.
Route Z between Business Loop 44 and Route J – Roadway resurfacing continues. The project is scheduled for completion in November.
Interstate 44 Spur between Route Y and Gateway Circle – Pavement milling and resurfacing continues. The project is scheduled for completion in November.
Daylight Hours
Route 133 between Route 7 and Route 17 – Pavement repair will take place Tuesday, September 3 through Thursday, September 12.
Washington County
Daylight Hours
Route C between Route 21 and Route Y – Pull paving will take place Tuesday, September 3 through Thursday, September 5.
MoDOT encourages motorists to log on to wwww.modot.org/modot-central-district to comment on their experiences traveling through highway work zones.
###