Update for Week of August 21-28
- Nighttime lane closings possible along southbound Route 65 between Sunshine Street and Route 60 to complete guardrail installation and shoulder work
- Northbound Route 65 CLOSINGS begin early Friday morning, September 6
- All new concrete pavement smoothed at the end of the project in late September
Work Scheduled:
- Rebuild shoulders in areas along southbound Route 65 between Sunshine Street and Route 60
- Install new guardrail in areas along southbound Route 65 between Sunshine Street and Route 60
- ADDITIONAL INFORMATION: All new concrete pavement will be smoothed using a diamond-grinding process at the end of the project in late September
Traffic Impacts:
- Night Work: One southbound lane closed in areas between Sunshine Street and Route 60. Work hours: 8 p.m. to 6 a.m.
- EARLY HEADS UP: Northbound Route 65 to CLOSE between Route 60 and Battlefield Road starting at 12:01 a.m. Friday, September 6, following the Labor Day holiday
- Temporary traffic signals in operation at Blackman Road/Battlefield Road and Greene County Route D/Route 125 intersections
- Signed detours:
- West detour: I-44 to eastbound Missouri Route 360 to eastbound U.S. Route 60 to southbound Route 65
- East detour: I-44 to Missouri Route 125 to westbound U.S. 60 to southbound Route 65
(Weather or construction delays could alter the work schedule.)
Project Summary:
- Sunday-Thursday, August 4-8 -- COMPLETE
- All southbound lanes of Route 65 CLOSED between Sunshine Street and Battlefield Road
- Southbound on ramp from Sunshine Street to Route 65 CLOSED
- Southbound off ramp from Route 65 to Battlefield Road CLOSED
- Thursday-Friday, August 8-16 -- COMPLETE
- All southbound lanes of Route 65 CLOSED between Battlefield Road and Route 60
- Southbound Route 65 OPEN between Sunshine Street and Battlefield Road, but reduced to one lane
- Southbound on ramp from Battlefield Road to Route 65 CLOSED
- Southbound Route 65-to-westbound Route 60 ramp CLOSED
All lanes of Route 65 open during the Labor Day holiday (Tuesday-Friday, August 20-September 6)
- Friday-Saturday, September 6-14
- All northbound lanes of Route 65 CLOSED between Route 60 and Battlefield Road
- Eastbound Route 60-to-northbound Route 65 ramp CLOSED
- Westbound Route 60-to-northbound Route 65 ramp CLOSED
- Northbound off ramp from Route 65 to Battlefield Road CLOSED
- Saturday-Friday, September 14-20
- All northbound lanes of Route 65 CLOSED between Battlefield Road and Sunshine Street
- Northbound Route 65 OPEN between Route 60 and Battlefield Road, but reduced to one lane
- Northbound on ramp from Battlefield Road to Route 65 CLOSED
- Northbound off ramp from Route 65 to Sunshine Street CLOSED
- Eastbound Route 60-to-northbound Route 65 ramp CLOSED
- Westbound Route 60-to-northbound Route 65 ramp CLOSED
- Route 60 crossovers CLOSED between Route 65 and Greene County Routes NN/J
- September 20-November 1
- Nighttime lane closings for shoulder construction/guardrail/striping/pavement smoothing
- Prime Contractor: Emery Sapp and Sons, Inc. of Columbia
- Completion Date: November 2019 (However, contractor plans to complete project by late September.)
- Total Project Cost: $8.1 million
END
(For more information, call MoDOT in Springfield at 417-895-7600 or visit www.modot.org/southwest)
(Follow MoDOT's Southwest District: Facebook | Twitter | Instagram |YouTube)
(For timely traffic information in the Springfield area, visit www.ozarkstraffic.com)
(Take the Challenge! Buckle Up/Phone Down)