TRAFFIC ALERT:

Southbound Route 65 OPEN Between Sunshine Street and Route 60 in Springfield

What:

  • Southbound Route 65 OPEN between Sunshine Street and Route 60 in Springfield, but reduced to one lane in areas until 7 a.m. Saturday, August 17
  • Ramp from Battlefield Road to southbound Route 65 OPEN
  • Southbound Route 65-to-westbound Route 60 ramp OPEN
  • Southbound Route 65 pavement reconstruction completed four days ahead of schedule 

When: Starting at 11:30 p.m. tonight (Friday, August 16) 

Additional Traffic Information:

  • ALL SOUTHBOUND LANES OF ROUTE 65 OPEN BETWEEN SUNSHINE STREET AND ROUTE 60 BY 7 A.M. SATURDAY, AUGUST 17
  • Nighttime lane closings needed as crews complete pavement striping, guardrail installation and shoulder work. Work hours: 8 p.m. to 7 a.m.
  • Temporary traffic signals in full operation at Battlefield Road and Blackman Road and at Greene County Route D and Route 125
    • Drivers urged to use caution at both intersections
  • REMINDER: Northbound Route 65 closings between Route 60 and Sunshine Street begin at 12:01 a.m. Friday, September 6, following the Labor Day holiday weekend 

(Weather or construction delays could alter the work schedule.) 

Project Summary:

  • Sunday-Thursday, August 4-8
    • All southbound lanes of Route 65 CLOSED between Sunshine Street and Battlefield Road
    • Southbound on ramp from Sunshine Street to Route 65 CLOSED
    • Southbound off ramp from Route 65 to Battlefield Road CLOSED
  • Thursday-Friday, August 8-16
    • All southbound lanes of Route 65 CLOSED between Battlefield Road and Route 60
    • Southbound Route 65 OPEN between Sunshine Street and Battlefield Road, but reduced to one lane
    • Southbound on ramp from Battlefield Road to Route 65 CLOSED
    • Southbound Route 65-to-westbound Route 60 ramp CLOSED 

All lanes of Route 65 open during the Labor Day holiday (Friday-Friday, August 16-September 6) 

  • Friday-Saturday, September 6-14
    • All northbound lanes of Route 65 CLOSED between Route 60 and Battlefield Road
    • Eastbound Route 60-to-northbound Route 65 ramp CLOSED
    • Westbound Route 60-to-northbound Route 65 ramp CLOSED
    • Northbound off ramp from Route 65 to Battlefield Road CLOSED
    • Route 60 crossovers CLOSED between Route 65 and Greene County Routes NN/J
  • Saturday-Friday, September 14-20
    • All northbound lanes of Route 65 CLOSED between Battlefield Road and Sunshine Street
    • Northbound Route 65 OPEN between Route 60 and Battlefield Road, but reduced to one lane
    • Northbound on ramp from Battlefield Road to Route 65 CLOSED
    • Northbound off ramp from Route 65 to Sunshine Street CLOSED
    • Eastbound Route 60-to-northbound Route 65 ramp CLOSED
    • Westbound Route 60-to-northbound Route 65 ramp CLOSED
    • Route 60 crossovers CLOSED between Route 65 and Greene County Routes NN/J
  • September 20-November 1
    • Nighttime lane closings for shoulder construction/guardrail/striping/pavement smoothing 
  • Prime Contractor: Emery Sapp and Sons, Inc. of Columbia
  • Completion Date: November 2019 (However, contractor plans to complete project by late September.)
  • Total Project Cost: $8.1 million

 END 



(For more information, call MoDOT in Springfield at 417-895-7600 or visit www.modot.org/southwest



(Follow MoDOT's Southwest District:
Facebook | Twitter | Instagram |YouTube)



(For timely traffic information in the Springfield area, visit
www.ozarkstraffic.com) 

(Take the Challenge! Buckle Up/Phone Down)

 

Districts Involved
Southwest