Route 65: THE REBUILD The Final Phase - Springfield

Update for Week of August 14-21
  • Southbound Route 65 between Battlefield Road and Route 60 scheduled to OPEN by Friday or Saturday, August 16 or 17
  • Nighttime lane closings possible after southbound Route 65 opens to complete pavement striping, guardrail installation and shoulder work                                            

Work Scheduled:  

  • Finish paving original lanes of southbound Route 65 between Battlefield Road and Route 60
  • Install guardrail in areas along southbound Route 65 between Sunshine Street and Route 60
  • Rebuild shoulders in areas along southbound Route 65 between Sunshine Street and Route 60
  • Complete pavement striping on southbound Route 65 between Sunshine Street and Route 60 

Traffic Impacts:  

  • Southbound Route 65 scheduled to REOPEN between Battlefield Road and Route 60 by late Friday or Saturday, August 16 or 17
    • At the same time, the following ramps will reopen
    • Ramp from Battlefield Road to southbound Route 65 CLOSED
    • Ramp from southbound Route 65-to-westbound Route 60 CLOSED
  • Night Work: One southbound lane closed in areas between Sunshine Street and Route 60. Work hours: 8 p.m. to 6 a.m.
  • Temporary traffic signals in operation at Blackman Road/Battlefield Road and Greene County Route D/Route 125 intersections
  • Signed detours:
    • West detour: I-44 to eastbound Missouri Route 360 to eastbound U.S. Route 60 to southbound Route 65
    • East detour: I-44 to Missouri Route 125 to westbound U.S. 60 to southbound Route 65

(Weather or construction delays could alter the work schedule.)

Project Summary:

  • Sunday-Thursday, August 4-8
    • All southbound lanes of Route 65 CLOSED between Sunshine Street and Battlefield Road
    • Southbound on ramp from Sunshine Street to Route 65 CLOSED
    • Southbound off ramp from Route 65 to Battlefield Road CLOSED
  •  Thursday-Tuesday, August 8-20
    • All southbound lanes of Route 65 CLOSED between Battlefield Road and Route 60
    • Southbound Route 65 OPEN between Sunshine Street and Battlefield Road, but reduced to one lane
    • Southbound on ramp from Battlefield Road to Route 65 CLOSED
    • Southbound Route 65-to-westbound Route 60 ramp CLOSED

 All lanes of Route 65 open during the Labor Day holiday (Tuesday-Friday, August 20-September 6)

  •  Friday-Saturday, September 6-14
    • All northbound lanes of Route 65 CLOSED between Route 60 and Battlefield Road
    • Eastbound Route 60-to-northbound Route 65 ramp CLOSED
    • Westbound Route 60-to-northbound Route 65 ramp CLOSED
    • Northbound off ramp from Route 65 to Battlefield Road CLOSED
  •  Saturday-Friday, September 14-20
    • All northbound lanes of Route 65 CLOSED between Battlefield Road and Sunshine Street
    • Northbound Route 65 OPEN between Route 60 and Battlefield Road, but reduced to one lane
    • Northbound on ramp from Battlefield Road to Route 65 CLOSED
    • Northbound off ramp from Route 65 to Sunshine Street CLOSED
    • Eastbound Route 60-to-northbound Route 65 ramp CLOSED
    • Westbound Route 60-to-northbound Route 65 ramp CLOSED
    • Route 60 crossovers CLOSED between Route 65 and Greene County Routes NN/J
  •  September 20-November 1
    • Nighttime lane closings for shoulder construction/guardrail/striping 
  • Prime Contractor: Emery Sapp and Sons, Inc. of Columbia
  • Completion Date: November 2019 (However, contractor plans to complete project by late September.)
  • Total Project Cost: $8.1 million

 END 



(For more information, call MoDOT in Springfield at 417-895-7600 or visit
www.modot.org/southwest



(Follow MoDOT's Southwest District:
Facebook | Twitter | Instagram |YouTube)



(For timely traffic information in the Springfield area, visit
www.ozarkstraffic.com) 

(Take the Challenge! Buckle Up/Phone Down)