The Missouri Highways and Transportation Commission has approved a contract to replace two bridges in Gasconade County.
Don Schnieders Excavating was awarded a contract to replace the Route 19 bridge over Second Creek and the Route EE bridge over Dry Fork Creek. The contractor submitted the lowest bid of $1,510,065.
Work is expected to begin in spring 2017. Each road will be closed, and traffic will be detoured during the respective work.