March 16 Public Meeting CANCELLED
Greene County – A public meeting planned for March 16 for the upcoming replacement of the Greene County Route H bridge over the South Dry Sac Creek north of Springfield has been CANCELLED, the Missouri Department of Transportation said.
A change in the contractor’s schedule has resulted in the postponement of the bridge project until mid-summer.
When a new start date is determined, MoDOT will work with the contractor to reschedule a public meeting to provide project timelines.
Project Information:
- Replace existing bridge with a new structure
- New bridge raised two feet higher than existing bridge. Route H also will be raised to meet the new bridge.
- New bridge will be 32 feet wide, with two 11-foot driving lanes and five-foot shoulders
- New bridge will be 45 feet longer than existing bridge
- Route H will be CLOSED to traffic for approximately four months once construction begins
- Project completion: Dec. 1, 2017
- Prime contractor: Lehman Construction, California
- Construction cost: $654,475