Route 65 Six-Laning Project - Springfield

Update for Week of May 29, 2017
  • No work planned over Memorial Day holiday weekend. However, traffic shift and lower speed limits on Route 65 will remain in place.
  • Possible nighttime lane closings on Route 65 

Work Scheduled:  

  • Building bridge columns for new northbound Route 65 bridge over Springfield Lake
  • Paving operations in Route 65 median during nighttime hours 

Traffic Impacts:  

  • Nighttime lane closings possible at times on Route 65 south of Springfield Lake. Work hours: as early as 7 p.m. to 6 a.m.
  • Trucks entering and leaving Route 65 median in areas south of Springfield Lake
  • Kayakers and boaters on Springfield Lake urged to use caution while traveling under Route 65 bridges due to work overhead
  • NORTHBOUND ROUTE 65 TRAFFIC MOVED TO SOUTHBOUND SPRINGFIELD LAKE BRIDGE.
    • Slight traffic delays occurring northbound during morning rush hour
    • Northbound speed limit reduced to 45 mph; further reduced to 40 mph in crossovers
    • Route 65 will remain open to four lanes most of the time
    • Northbound traffic will remain on southbound bridge until late summer 2017
    • Southbound Route 65 ramp from eastbound Route 60 extended across Springfield Lake bridge. Drivers encouraged to use extended ramp and merge into southbound Route 65 after crossing bridge.
  • ROAD/TRAIL CLOSINGS:
    • Timbercrest Road underneath Route 65, the Galloway Greenways trail and the James River Water trail CLOSED until fall 2017
    • Drivers urged to use alternate routes to get around the Timbercrest Road closing
    • Trail users are urged to use other Greenways trails in the area
  • Route 65 speed limit reduced to 55 mph in work zone 

(Weather or construction delays could alter the work schedule.) 

Project Summary:

  • Widen Route 65 to six lanes — three lanes in each direction — between Route 60 and a point south of Evans Road to continue the progress to six lane Route 65 toward Ozark
  • Widen and rehabilitate southbound Route 65 bridge over Lake Springfield to accommodate new lanes and to lengthen eastbound Route 60-to-southbound Route 65 ramp
  • Replace northbound Route 65 bridge over Lake Springfield with new, wider span to replace old bridge in constant need of repair
  • Extend northbound Route 65 ramps to Route 60
  • Prime Contractor: Emery Sapp and Sons, Columbia
  • Completion Date: November 2017
  • Total Project Cost: $21 million

 Follow MoDOT's Southwest District:

  • Facebook: MoDOT.Southwest
  • Twitter: MoDOT_Southwest
  • Instagram: @MoDOT_Southwest
Districts Involved
Southwest
MODOT Newsroom

The newsroom is a one-stop shop for media partners to find their local and statewide communications contacts and news releases, as well as download department leadership portraits and other media.

Visit the Newsroom
Real Time Traffic

Monitor real time traffic with our online traffic map.