Update for Weeks of June 5 & 12, 2017
- Nighttime Route 65 lane closings for paving work in median areas
- Building bridge columns for new northbound Route 65 bridge over Springfield Lake
Work Scheduled:
- Building bridge columns for new northbound Route 65 bridge over Springfield Lake
- Paving operations in Route 65 median during nighttime hours
- Building concrete barrier in Route 65 median areas south of Evans Road
- Installing large rock under Route 65 bridge over Farmer’s Branch south of Evans Road
Traffic Impacts:
- Nighttime lane closings possible at times on Route 65 south of Springfield Lake. Work hours: as early as 7 p.m. to 6 a.m.
- Trucks entering and leaving Route 65 median in areas south of Springfield Lake
- Kayakers and boaters on Springfield Lake urged to use caution while traveling under Route 65 bridges due to work overhead
- NORTHBOUND ROUTE 65 TRAFFIC MOVED TO SOUTHBOUND SPRINGFIELD LAKE BRIDGE.
- Slight traffic delays occurring northbound during morning rush hour
- Northbound speed limit reduced to 45 mph; further reduced to 40 mph in crossovers
- Route 65 will remain open to four lanes most of the time
- Northbound traffic will remain on southbound bridge until late summer 2017
- Southbound Route 65 ramp from eastbound Route 60 extended across Springfield Lake bridge. Drivers encouraged to use extended ramp and merge into southbound Route 65 after crossing bridge.
- ROAD/TRAIL CLOSINGS:
- Timbercrest Road underneath Route 65, the Galloway Greenways trail and the James River Water trail CLOSED until fall 2017
- Drivers urged to use alternate routes to get around the Timbercrest Road closing
- Trail users are urged to use other Greenways trails in the area
- Route 65 speed limit reduced to 55 mph in work zone
(Weather or construction delays could alter the work schedule.)
Project Summary:
- Widen Route 65 to six lanes — three lanes in each direction — between Route 60 and a point south of Evans Road to continue the progress to six lane Route 65 toward Ozark
- Widen and rehabilitate southbound Route 65 bridge over Lake Springfield to accommodate new lanes and to lengthen eastbound Route 60-to-southbound Route 65 ramp
- Replace northbound Route 65 bridge over Lake Springfield with new, wider span to replace old bridge in constant need of repair
- Extend northbound Route 65 ramps to Route 60
- Prime Contractor: Emery Sapp and Sons, Columbia
- Completion Date: November 2017
- Total Project Cost: $21 million