Update for Weeks of June 5 & 12, 2017
- Nighttime Lane Closings Planned for Route 65 between Sunshine Street and Kearney Street
Work Scheduled:
- Crews surveying to get exact measurements of pavement to be replaced
- Other prep work ahead of pavement replacement project
Traffic Impacts:
- Week of June 5:
- Two southbound lanes of Route 65 closed
- Work hours: 8 p.m. to 6 a.m.
- One southbound lane remains open during work
- Week of June 12:
- Two northbound lanes of Route 65
- Work hours: 8 p.m. to 6 a.m.
- One northbound lane remains open during work
- Full CLOSINGS of southbound or northbound Route 65 will not start until week of July 10
(Weather or construction delays could alter the work schedule.)
Project Summary:
- Rebuild outside two lanes in both directions of Route 65 between Kearney Street and Sunshine Street
- Route 65 CLOSED in segments (between interchanges) in one direction at a time from week of July 10 until first of September
- Rebuild or repair interchange ramps
- Upgrade guardrail
- Rebuild outside shoulders
- Prime Contractor: Millstone Weber, LLC of St. Charles, Mo.
- Completion Date: November 2017
- Total Project Cost: $7.9 million