Route 65: THE REBUILD - Springfield

Update for Week of July 10, 2017 -- ROUTE 65 CLOSINGS SET TO BEGIN

THINGS TO KNOW ABOUT THE PROJECT THIS COMING WEEK:

  • Southbound Route 65 CLOSED between Kearney and Division Streets at 12:01 a.m. Monday, July 10, until as late as 11:59 p.m. on Sunday, July 16
  • I-44 ramps to southbound Route 65 CLOSED when southbound Route 65 closes July 10                                            

Work Scheduled:  

  • Breaking up and removing concrete pavement in two southbound outside lanes of Route 65 between Kearney and Division streets early in the week
  • Pouring new concrete for southbound outside lanes starting on Tuesday or Wednesday
  • Rebuilding southbound on ramp from Kearney Street to Route 65 and southbound off ramp from Route 65 to Division Street
  • Crews working 24-hours a day with construction noise possible ‘round the clock 

Traffic Impacts:  

  • ROAD CLOSED: Southbound Route 65 CLOSED between Kearney Street and Division Street
    • Closing timeline: 12:01 a.m. Monday, July 10, until as late as 11:59 p.m. on Sunday, July 16
    • Southbound Route 65 reduced to one lane south of I-44 to Kearney Street
    • All southbound Route 65 traffic must exit at Kearney Street
    • RAMPS CLOSED:
      • I-44 ramps to southbound Route 65 CLOSED
      • Southbound on ramp from Kearney Street to Route 65 CLOSED
      • Southbound off ramp from Route 65 to Division Street CLOSED
    • ROUTE 65 DETOUR:
      • Signed detour using I-44 and Route 360/60 (southwest loop around Springfield)
      • Drivers encouraged to find alternate routes to destinations inside Springfield including Glenstone Avenue, Kansas Expressway and West Bypass
    • TEMPORARY TRAFFIC SIGNALS:
      • Located at Eastgate Avenue & Cherry Street, Eastgate Avenue & Catalpa Street, and LeCompte Road & Division Street intersections
      • Traffic signals in full operation starting at 12:01 a.m. on Monday, July 10, when closings of Route 65 begin
      • Drivers will experience delays at the intersections when the new traffic signals go into full operation

 

(Weather or construction delays could alter the work schedule.)

 Project Summary:

  • Rebuild outside two lanes in both directions of Route 65 between Kearney Street and Sunshine Street
  • Route 65 CLOSED in segments (between interchanges) in one direction at a time from week of July 10 until first of September
  • Southbound closings start on July 10 with completion by late July/early August
    • Southbound closed between Kearney and Division Streets week of July 10
    • Southbound closed between Division Street and Chestnut Expressway week of July 17
    • Southbound closed between Chestnut Expressway and Sunshine Street week of July 24
  • Northbound closings start on August 7 with completion by late August/early September
    • Northbound closed between Sunshine Street and Chestnut Expressway week of August 7
    • Northbound closed between Chestnut Expressway and Division Street week of August 14
    • Northbound closed between Division Street and Kearney Street week of August 21
  • Rebuild or repair interchange ramps
  • Upgrade guardrail
  • Rebuild outside shoulders
  • Prime Contractor: Millstone Weber, LLC of St. Charles, Mo.
  • Completion Date: November 2017
  • Total Project Cost: $7.9 million

 

END 

(For more information, call MoDOT in Springfield at 417-895-7600 or visit www.modot.org/southwest

(Follow MoDOT's Southwest District: Facebook | Twitter | Instagram |YouTube)

(For timely traffic information in the Springfield area, visit www.ozarkstraffic.com)

Districts Involved
Southwest
MODOT Newsroom

The newsroom is a one-stop shop for media partners to find their local and statewide communications contacts and news releases, as well as download department leadership portraits and other media.

Visit the Newsroom
Real Time Traffic

Monitor real time traffic with our online traffic map.