Update for Week of July 10, 2017 -- ROUTE 65 CLOSINGS SET TO BEGIN
THINGS TO KNOW ABOUT THE PROJECT THIS COMING WEEK:
- Southbound Route 65 CLOSED between Kearney and Division Streets at 12:01 a.m. Monday, July 10, until as late as 11:59 p.m. on Sunday, July 16
- I-44 ramps to southbound Route 65 CLOSED when southbound Route 65 closes July 10
Work Scheduled:
- Breaking up and removing concrete pavement in two southbound outside lanes of Route 65 between Kearney and Division streets early in the week
- Pouring new concrete for southbound outside lanes starting on Tuesday or Wednesday
- Rebuilding southbound on ramp from Kearney Street to Route 65 and southbound off ramp from Route 65 to Division Street
- Crews working 24-hours a day with construction noise possible ‘round the clock
Traffic Impacts:
- ROAD CLOSED: Southbound Route 65 CLOSED between Kearney Street and Division Street
- Closing timeline: 12:01 a.m. Monday, July 10, until as late as 11:59 p.m. on Sunday, July 16
- Southbound Route 65 reduced to one lane south of I-44 to Kearney Street
- All southbound Route 65 traffic must exit at Kearney Street
- RAMPS CLOSED:
- I-44 ramps to southbound Route 65 CLOSED
- Southbound on ramp from Kearney Street to Route 65 CLOSED
- Southbound off ramp from Route 65 to Division Street CLOSED
- ROUTE 65 DETOUR:
- Signed detour using I-44 and Route 360/60 (southwest loop around Springfield)
- Drivers encouraged to find alternate routes to destinations inside Springfield including Glenstone Avenue, Kansas Expressway and West Bypass
- TEMPORARY TRAFFIC SIGNALS:
- Located at Eastgate Avenue & Cherry Street, Eastgate Avenue & Catalpa Street, and LeCompte Road & Division Street intersections
- Traffic signals in full operation starting at 12:01 a.m. on Monday, July 10, when closings of Route 65 begin
- Drivers will experience delays at the intersections when the new traffic signals go into full operation
(Weather or construction delays could alter the work schedule.)
Project Summary:
- Rebuild outside two lanes in both directions of Route 65 between Kearney Street and Sunshine Street
- Route 65 CLOSED in segments (between interchanges) in one direction at a time from week of July 10 until first of September
- Southbound closings start on July 10 with completion by late July/early August
- Southbound closed between Kearney and Division Streets week of July 10
- Southbound closed between Division Street and Chestnut Expressway week of July 17
- Southbound closed between Chestnut Expressway and Sunshine Street week of July 24
- Northbound closings start on August 7 with completion by late August/early September
- Northbound closed between Sunshine Street and Chestnut Expressway week of August 7
- Northbound closed between Chestnut Expressway and Division Street week of August 14
- Northbound closed between Division Street and Kearney Street week of August 21
- Rebuild or repair interchange ramps
- Upgrade guardrail
- Rebuild outside shoulders
- Prime Contractor: Millstone Weber, LLC of St. Charles, Mo.
- Completion Date: November 2017
- Total Project Cost: $7.9 million
END
(For more information, call MoDOT in Springfield at 417-895-7600 or visit www.modot.org/southwest)
(Follow MoDOT's Southwest District: Facebook | Twitter | Instagram |YouTube)