Update for Week of July 24, 2017
THINGS TO KNOW ABOUT THE PROJECT IN THE COMING WEEK:
- Southbound Route 65 CLOSED between Chestnut Expressway and a point north of Sunshine Street at approximately 8 p.m. on Sunday evening, July 23
- Southbound Route 65 OPEN from I-44 to Chestnut Expressway after 8 p.m. Sunday evening, July 23
- Southbound Route 65 reduced to one lane between a point south of I-44 to Chestnut Expressway
- Drivers urged to avoid Eastgate Avenue east of Route 65 especially at Chestnut Expressway
- Delays expected for drivers existing southbound Route 65 at Chestnut Expressway due to bridge construction and crossing trains
- ALL SOUTHBOUND LANES OF ROUTE 65 EXPECTED TO OPEN TO TRAFFIC BY LATE ON SUNDAY, JULY 30
Work Scheduled:
- Breaking up and removing concrete pavement in two southbound outside lanes of Route 65 between Chestnut Expressway and a point north of Sunshine Street early in the week
- Pouring new concrete for southbound outside lanes starting on Tuesday or Wednesday
- Installing guardrail in areas between Kearney Street and Chestnut Expressway
- Crews working 24-hours a day with construction noise possible ‘round the clock
Traffic Impacts:
- ROAD CLOSED: Southbound Route 65 CLOSED between Chestnut Expressway and Sunshine Street
- Closing time: around 8 p.m. on Sunday, July 23, until as late as 11:59 p.m. on Sunday, July 30
- Southbound Route 65 reduced to one lane south of I-44 to Chestnut Expressway
- All southbound Route 65 traffic can and must exit at Chestnut Expressway
- Southbound Route 65 traffic can exit at Kearney Street and at Division Street
- RAMPS CLOSED:
- I-44 ramps to southbound Route 65 CLOSED
- Southbound on ramp from Chestnut Expressway to Route 65 CLOSED
- Southbound off ramp from Route 65 to Sunshine Street CLOSED
- ROUTE 65 DETOUR:
- Signed detour using I-44 and Route 360/60 (southwest loop around Springfield)
- Alternate detour using Route 125 between I-44 and Route 60
- Drivers encouraged to find alternate routes to destinations inside Springfield including Glenstone Avenue, Kansas Expressway and West Bypass
- TEMPORARY TRAFFIC SIGNALS:
- Located at Eastgate Avenue & Cherry Street, Eastgate Avenue & Catalpa Street, and LeCompte Road & Division Street intersections
- Drivers will experience delays at the intersections
- Traffic signals are temporary and will be removed when the closings of Route 65 are complete in late August/early September
(Weather or construction delays could alter the work schedule.)
Project Summary:
- Rebuild outside two lanes in both directions of Route 65 between Kearney Street and Sunshine Street
- Route 65 CLOSED in segments (between interchanges) in one direction at a time from week of July 10 until first of September
- Southbound closings start on July 10 with completion by late July/early August
- Southbound closed between Kearney and Division Streets week of July 10 -- COMPLETED
- Southbound closed between Division Street and Chestnut Expressway week of July 17 – NEARING COMPLETION
- Southbound closed between Chestnut Expressway and Sunshine Street week of July 24
- Northbound closings start on August 7 with completion by late August/early September
- Northbound closed between Sunshine Street and Chestnut Expressway week of August 7
- Northbound closed between Chestnut Expressway and Division Street week of August 14
- Northbound closed between Division Street and Kearney Street week of August 21
- Rebuild or repair interchange ramps
- Upgrade guardrail
- Rebuild outside shoulders
- Prime Contractor: Millstone Weber, LLC of St. Charles, Mo.
- Completion Date: November 2017
- Total Project Cost: $7.9 million
END
(For more information, call MoDOT in Springfield at 417-895-7600 or visit www.modot.org/southwest)
(Follow MoDOT's Southwest District: Facebook | Twitter | Instagram |YouTube)
(For timely traffic information in the Springfield area, visit www.ozarkstraffic.com)
Districts Involved
Southwest
Published On