Route 65: THE REBUILD - Springfield

Update for Week of July 31, 2017

THINGS TO KNOW ABOUT THE PROJECT IN THE COMING WEEK:

  • Southbound Route 65 SCHEDULED TO OPEN between Chestnut Expressway and Sunshine Street by midnight Sunday, July 30
  • ALL LANES OF ROUTE 65 OPEN DURING DAYTIME HOURS WEEK OF JULY 31
  • NORTHBOUND ROUTE 65 BETWEEN SUNSHINE STREET AND CHESTNUT EXPRESSWAY SCHEDULED TO CLOSE AT 12:01 A.M. MONDAY, AUGUST 7                                            

Work Scheduled:  

  • Sawing concrete pavement at night in two outside lanes of northbound Route 65 between Sunshine and Kearney Streets, prepping for removal starting week of August 7
  • Cleanup work at night on southbound Route 65 in areas between Kearney Street and Sunshine Street 

Traffic Impacts:  

  • NIGHTTIME LANE CLOSINGS: Up to two northbound and/or southbound lanes of Route 65 closed at times between Kearney and Sunshine Streets. Work hours: 8 p.m. to 6 a.m. Monday-Friday.
  • All lanes of Route 65 OPEN during daytime hours
  • All southbound Route 65 ramps OPEN between Kearney and Sunshine streets
  • All I-44 ramps OPEN at Route 65
  • TEMPORARY TRAFFIC SIGNALS:
    • Located at Eastgate Avenue & Cherry Street, Eastgate Avenue & Catalpa Street, and LeCompte Road & Division Street intersections
    • Drivers will experience delays at the intersection
    • Traffic signals are temporary and will be removed when the closings of Route 65 are complete in late August/early September 

(Weather or construction delays could alter the work schedule.) 

Project Summary:

  • Rebuild outside two lanes in both directions of Route 65 between Kearney Street and Sunshine Street
  • Route 65 CLOSED in segments (between interchanges) in one direction at a time from week of July 10 until first of September
  • Southbound closings start on July 10 with completion by late July/early August
    • Southbound closed between Kearney and Division Streets week of July 10 -- COMPLETED
    • Southbound closed between Division Street and Chestnut Expressway week of July 17 – COMPLETED
    • Southbound closed between Chestnut Expressway and Sunshine Street week of July 24 – NEARING COMPLETION
  • Northbound closings start on August 7 with completion by late August/early September
    • Northbound closed between Sunshine Street and Chestnut Expressway week of August 7
    • Northbound closed between Chestnut Expressway and Division Street week of August 14
    • Northbound closed between Division Street and Kearney Street week of August 21
  • Rebuild or repair interchange ramps
  • Upgrade guardrail
  • Rebuild outside shoulders
  • Prime Contractor: Millstone Weber, LLC of St. Charles, Mo.
  • Completion Date: November 2017
  • Total Project Cost: $7.9 million

END 

(For more information, call MoDOT in Springfield at 417-895-7600 or visit www.modot.org/southwest

(Follow MoDOT's Southwest District: Facebook | Twitter | Instagram |YouTube)

(For timely traffic information in the Springfield area, visit www.ozarkstraffic.com)

Districts Involved
Southwest
MODOT Newsroom

The newsroom is a one-stop shop for media partners to find their local and statewide communications contacts and news releases, as well as download department leadership portraits and other media.

Visit the Newsroom
Real Time Traffic

Monitor real time traffic with our online traffic map.