Route 65: THE REBUILD - Springfield

Update for Week of August 7, 2017

THINGS TO KNOW ABOUT THE PROJECT IN THE COMING WEEK:

  • NORTHBOUND ROUTE 65 BETWEEN SUNSHINE STREET AND CHESTNUT EXPRESSWAY TO CLOSE AT 12:01 A.M. MONDAY, AUGUST 7, until as late as 11:59 pm on Sunday, August 13
  • All northbound Route 65 traffic can and must exit at Sunshine Street                                            

Work Scheduled:  

  • Breaking up and removing concrete pavement in two northbound outside lanes of Route 65 between Sunshine Street and Chestnut Expressway early in the week
  • Pouring new concrete for northbound outside lanes starting on Tuesday or Wednesday
  • Crews working 24-hours a day with construction noise possible ‘round the clock 

Traffic Impacts:  

  • ROAD CLOSED: Northbound Route 65 CLOSED between Sunshine Street and Chestnut Expressway
    • Closing time: 12:01 a.m. Monday, August 7, until as late as 11:59 p.m. on Sunday, August 13
    • All northbound Route 65 traffic can and must exit at Sunshine Street
  • RAMPS CLOSED:
    • Northbound on ramp from Sunshine Street to Route 65 CLOSED
    • Northbound off ramp from Route 65 to Chestnut Expressway CLOSED
  • ROUTE 65 DETOUR:
    • Signed detour using Route 60/360 to I-44
    • Alternate detour using Route 125 between Route 60 and I-44
    • Drivers encouraged to find alternate routes to destinations inside Springfield including Glenstone Avenue, Kansas Expressway and West Bypass
  • TEMPORARY TRAFFIC SIGNALS:
    • Located at Eastgate Avenue & Cherry Street, Eastgate Avenue & Catalpa Street, and LeCompte Road & Division Street intersections
    • Drivers will experience delays at the intersections
    • Traffic signals are temporary and will be removed when the closings of Route 65 are complete in late August/early September 

(Weather or construction delays could alter the work schedule.) 

Project Summary:

  • Rebuild outside two lanes in both directions of Route 65 between Kearney Street and Sunshine Street
  • Route 65 CLOSED in segments (between interchanges) in one direction at a time from week of July 10 until first of September
  • Southbound closings start on July 10 with completion by late July/early August
    • Southbound closed between Kearney and Division Streets week of July 10 -- COMPLETED
    • Southbound closed between Division Street and Chestnut Expressway week of July 17 – COMPLETED
    • Southbound closed between Chestnut Expressway and Sunshine Street week of July 24 – COMPLETED
  • Northbound closings start on August 7 with completion by late August/early September
    • Northbound closed between Sunshine Street and Chestnut Expressway week of August 7
    • Northbound closed between Chestnut Expressway and Division Street week of August 14
    • Northbound closed between Division Street and Kearney Street week of August 21
  • Rebuild or repair interchange ramps
  • Upgrade guardrail
  • Rebuild outside shoulders
  • Prime Contractor: Millstone Weber, LLC of St. Charles, Mo.
  • Completion Date: November 2017
  • Total Project Cost: $7.9 million

END 

(For more information, call MoDOT in Springfield at 417-895-7600 or visit www.modot.org/southwest

(Follow MoDOT's Southwest District: Facebook | Twitter | Instagram |YouTube)

(For timely traffic information in the Springfield area, visit www.ozarkstraffic.com)

 

Districts Involved
Southwest
MODOT Newsroom

The newsroom is a one-stop shop for media partners to find their local and statewide communications contacts and news releases, as well as download department leadership portraits and other media.

Visit the Newsroom
Real Time Traffic

Monitor real time traffic with our online traffic map.