Update for Week of September 11, 2017
THINGS TO KNOW ABOUT THE PROJECT IN THE COMING WEEK:
- Nighttime lane closings on Route 65 between Sunshine and Kearney Streets throughout the week
Work Scheduled:
- Paving roadway shoulders in areas
- Installing new guardrail in areas
Traffic Impacts:
- ALL LANES OF ROUTE 65 OPEN during daytime hours
- NIGHT WORK: Lane closings in both northbound and southbound lanes of Route 65. Work hours: 8 p.m. to 6 a.m. Monday-Friday.
(Weather or construction delays could alter the work schedule.)
Project Summary:
- Rebuild outside two lanes in both directions of Route 65 between Kearney Street and Sunshine Street
- Route 65 CLOSED in segments (between interchanges) in one direction at a time from week of July 10 until first of September
- Northbound closings COMPLETE as of August 27
- Northbound closed between Sunshine Street and Chestnut Expressway week of August 7 – COMPLETED
- Northbound closed between Chestnut Expressway and Division Street week of August 14 -- COMPLETED
- Northbound closed between Division Street and Kearney Street week of August 21 -- COMPLETED
- Southbound closings COMPLETE as of July 30
- Southbound closed between Kearney and Division Streets week of July 10 -- COMPLETED
- Southbound closed between Division Street and Chestnut Expressway week of July 17 – COMPLETED
- Southbound closed between Chestnut Expressway and Sunshine Street week of July 24 – COMPLETED
- Rebuild or repair interchange ramps
- Upgrade guardrail
- Rebuild outside shoulders
- Prime Contractor: Millstone Weber, LLC of St. Charles, Mo.
- Completion Date: November 2017
- Total Project Cost: $7.9 million
END
(For more information, call MoDOT in Springfield at 417-895-7600 or visit www.modot.org/southwest)
(Follow MoDOT's Southwest District: Facebook | Twitter | Instagram |YouTube)
(For timely traffic information in the Springfield area, visit www.ozarkstraffic.com)