Update for Weeks of October 23 and 30
- Boat traffic restricted underneath north side of Bull Shoals Lake bridge
Work Scheduled:
- Building bridge columns for north end of new Route 76 bridge over Bull Shoals Lake
- Hauling rock and dirt to south side of bridge
Traffic Impacts:
- Occasional one-lane traffic on Route 76 on bridge. Work hours: between morning and evening rush hours during week of Oct. 30. Flaggers directing drivers through work zone.
- Baker Street CLOSED on south side of bridge
- Boat traffic restricted underneath north side of bridge
(Weather or construction delays could alter the work schedule.)
Project Summary:
- Replace Bull Shoals Lake bridge with a new bridge west of the existing bridge
- Connect new bridge to Route 76 at end of bridge project
- Completion Date: Fall 2018
- Total Project Cost: $10.4 million
END
(For more information, call MoDOT in Springfield at 417-895-7600 or visit www.modot.org/southwest)
(Follow MoDOT's Southwest District: Facebook | Twitter | Instagram |YouTube) (
For timely traffic information in the Springfield area, visit www.ozarkstraffic.com)
Districts Involved
Southwest