Update for Week of April 23
- New traffic signal at Chestnut Expressway and Ingram Mill Road goes into full operation Wednesday, April 25
Work Scheduled:
- Installing roads signs in various locations
- Applying pavement striping
- Laying sod and applying grass seed and mulch in various locations
Traffic Impacts:
- CAUTION: New traffic signal goes into full operation at Chestnut Expressway and Ingram Mill Road on Wednesday, April 25.
- Drivers should expect to stop on Chestnut Expressway at the new signal
- CHESTNUT EXPRESSWAY OPEN TO FOUR LANES
- Lane closings possible at times on Chestnut Expressway between Ingram Mill Road and Belcrest Avenue
- Camera view of project
(Weather or construction delays could alter the work schedule.)
Project Summary:
- Build a bridge on Chestnut Expressway over the railroad tracks west of Route 65
- Build new roads on either side of Chestnut Expressway to provide access to area businesses
- Install a new traffic signal at Ingram Mill Road and Chestnut Expressway
- First phase of construction: June to December 2016. Prime contractor: D&E Blasting & Excavating, Nixa -- COMPLETED
- Second phase of construction: January 2017 to November 2017. Prime contractor: Lehman Construction Company, California
- Partnership project: Springfield, Greene County, Burlington Northern-Santa Fe Railroad & MoDOT
- Project nearing completion
- Total Project Cost: $14.8 million
END
(For more information, call MoDOT in Springfield at 417-895-7600 or visit www.modot.org/southwest)
(Follow MoDOT's Southwest District: Facebook | Twitter | Instagram |YouTube)
(For timely traffic information in the Springfield area, visit www.ozarkstraffic.com)
Districts Involved
Southwest
Published On