Update for Week of May 28
- No work planned on Monday, May 28, during the Memorial Day holiday
- Inside northbound and southbound lanes of Glenstone Avenue at Kearney Street and Evergreen Street closed ‘round the clock starting Tuesday, May 29
Work Scheduled:
- Removing concrete pavement from the inside lanes of Glenstone Avenue at Kearney Street and at Evergreen Street
Traffic Impacts:
- Inside northbound and southbound lanes of Glenstone Avenue closed at Kearney Street and at Evergreen street ‘round the clock
- Drivers will not be able to make left turns at Evergreen Street
- One northbound and one southbound lane of Glenstone Avenue will remain open most of the time
- Drivers can expect delays
(Weather or construction delays could alter the work schedule.)
Project Summary:
- Rebuild the deteriorating concrete pavement on Glenstone Avenue in four separate locations
- At Evergreen Street south of I-44
- At Kearney Street
- At the railroad overpass north of Commercial Street
- Between Lombard Street and Page Street
- Sections at Kearney Street and at Evergreen Street under construction from May 29 until July 4
- Sections at railroad overpass near Commercial Street and between Lombard Street and Page Street under construction starting in July or August
- Total Project Cost: $3.7 million
- Completion Date: November 1, 2018
END
(For more information, call MoDOT in Springfield at 417-895-7600 or visit www.modot.org/southwest)
(Follow MoDOT's Southwest District: Facebook | Twitter | Instagram |YouTube)
(For timely traffic information in the Springfield area, visit www.ozarkstraffic.com)