The following is a listing of general highway maintenance and construction work in the mid-Missouri area for the two-week period of June 4 - 15, 2018. Weather conditions may postpone the work schedule. Many projects will include lane closures that could cause delays.
MoDOT reminds motorists to buckle up, slow down, follow posted signs and drive safely through work areas. For more information about a project, please contact MoDOT at 1-888-ASK-MoDOT (275-6636) or visit www.modot.org/central. You can also follow MoDOT’s Central Missouri District on Twitter and Facebook at https://twitter.com/MoDOT_Central and MoDOT Central Missouri District.
All Counties
Daylight Hours
Mowing, striping, brush cutting and guardrail repair continue in various locations. Motorists should travel with care and be alert to slow-moving equipment along the road.
Boone County
Daylight/Overnight Hours
Route 63 at Bonne Femme Creek, south of Discovery Parkway – Bridge improvements and acceleration lane construction in the southbound lanes continue. One southbound lane is closed through the work area.
* The project is now in Phase 2. All southbound traffic has been shifted into the southbound driving lane with a decreased lane width of 12 feet.
*Access to Route 63 from Tom Bass Road is closed.
*All lanes are expected to reopen to traffic in June.
The project is scheduled for completion in October.
Route 124 between Route B and Route CC – Resurfacing and shoulder improvements continue. Resurfacing operations will take place during the overnight hours the week of June 4. The project is scheduled for completion in June.
Overnight Hours
Sorrells Overpass Drive over Interstate 70 – Bridge maintenance will take place Monday, June 11 through Wednesday, June 13. One lane will be open, and crews will flag traffic through the work area.
Route 163 between Route AC and Carter Lane – Concrete repair in the northbound lane will take place Monday, June 11 and Tuesday, June 12 between 8 p.m. and 6 a.m. One northbound lane will be open, and crews will flag traffic through the work area.
Interstate 70 Outer Road between Route 740 (Stadium Boulevard) and Knipp Street – Culvert pipe replacement will take place Wednesday, June 13 and Thursday, June 14. The road will be closed. Motorist are advised to seek an alternate route.
Daylight Hours
Route B between Business Loop 70 and Brown Station Road – Roadway resurfacing and sidewalk improvements continue.
* ADA and sidewalk upgrades between Route 63 and Business Loop 70 will continue the week of June 4. The project is scheduled for completion in June.
Callaway County
Daylight/Overnight Hours
Route 54 Bridge Improvements
Here is a look at traffic impacts currently in place near the U.S. Route 54 bridges over Ozark Valley Railroad, Richland Creek and Business Route 54:
* Guard cable installation on the eastbound and westbound Route 54 from Holts Summit to Route HH in Fulton
* Bridge rehabilitation work on the eastbound Route 54 over Stinson Creek. One eastbound lane of Route 54 will be closed through the work area.
These traffic impacts are scheduled until the end of July.
Camden County
Daylight/Overnight Hours
Route 54 Outer Road over Linn Creek – Bridge replacement continues. One eastbound lane will be open through the work area.
* Westbound motorists will need to use the U.S. Route 54 crossover to connect with the Route 54 east crossover to travel east across the Outer Road bridge. The project is scheduled for completion in July.
Route 5 between Route 7 and the Niangua River – Roadway resurfacing continues. One lane will be open, and crews will flag traffic through the work area. The project is scheduled for completion in November.
Daylight
Route A between Route 54 and Route 7 – Culvert pipe repair will take place Monday, June 4 through Thursday, June 14. One lane will be open, and crews will flag traffic through the work area.
Route NN between Route 7 and Bannister Hollow Road – Culvert pipe repair will take place Monday, June 4 through Thursday, June 14. One lane will be open, and crews will flag traffic through the work area.
Cole County
Daylight/Overnight Hours
Route 54 between Broadway Street and Stadium Boulevard – Roadway resurfacing, pavement repair, guard rail replacement and bridge repair is continues.
* Rehabilitation work on the eastbound Route 54 bridges over Stadium Boulevard and Broadway Street continues. One eastbound lane will be open through the work area. The eastbound bridge work is scheduled for completion in mid-June.
* The eastbound entrance ramp from Christy Drive to Route 54 is closed.
Entire project is scheduled for completion in November.
Route 17 over Route 54, south of Redfield Drive– Bridge maintenance will take place Monday, June 4 through Thursday, June 7. One lane will be open, and crews will flag traffic through the work area.
Cooper County
Overnight Hours
Interstate 70 over the Missouri River – Bridge maintenance will take place Sunday, June 10 and Monday, June 11. One lane will be open, and crews will flag traffic through the work area.
Daylight Hours
Route W between Route J and Clarksburg Drive – Pavement patching will take place Monday, June 4 through Thursday, June 7. One lane will be open, and crews will flag traffic through the work area.
Crawford County
Daylight Hours
Interstate 44 between Route H and Route ZZ – Pavement patching will begin the week of June 4. One lane will be open through the work area. Project is scheduled for completion in November.
Route 19 between Route P and Wildcat Pride Drive – Pavement marking will take place Monday, June 4 through Thursday, June 7. One lane will be open, and crews will flag traffic through the work area.
Route M between Route 8 and Route YY – Roadside work will take place Monday, June 4 through Thursday, June 7. One lane will be open, and crews will flag traffic through the work area.
Route AA between Route 19 and Cherryville Road – Roadway patching will take place Monday, June 4 through Thursday, June 14. One lane will be open, and crews will flag traffic through the work area.
Route BB between Route 8 and Westover Road – Roadway patching will take place Monday, June 4 through Thursday, June 14. One lane will be open, and crews will flag traffic through the work area.
Route PP between Route 19 and Bass Road – Roadway patching will take place Monday, June 4 through Thursday, June 14. One lane will be open, and crews will flag traffic through the work area.
Route VV between Route 19 and Route M – Roadway patching will take place Monday, June 4 through Thursday, June 14. One lane will be open, and crews will flag traffic through the work area.
Route YY between Route 68 and Route M – Roadside work will take place Monday, June 4 through Thursday, June 14. One lane will be open, and crews will flag traffic through the work area.
Dent County
Daylight/Overnight Hours
Route 32 between Route 72 and Route 63 in Texas County – Roadway resurfacing continues.
*One lane will be open and crews and a pilot car will guide traffic through the work area. The project is scheduled for completion in the fall.
Daylight
Route 119 between Route 32 and County Road 6670 – Roadway resurfacing continues.
*One lane will be open and crews and a pilot car will guide traffic through the work area. The project is scheduled for completion in the fall.
Route F over Holt Creek, South of Route 32 – Bridge replacement continues.
*The road will be closed to traffic during the project.
Motorists should use the signed detour around the closure. The project is scheduled for completion in early August.
Gasconade County
Daylight Hours
Route 19 between Route 28 and Route 50 – Shoulder addition and asphalt paving continues. One lane will be open, and crews will flag traffic through the work area.
Route F between Route 19 and Route J – Pavement patching will take place Monday, June 4 through Thursday, June 14. One lane will be open, and crews will flag traffic through the work area.
Route J between Route 100 and Toll Ferry Road – Pavement patching will take place Monday, June 4 through Thursday, June 14. One lane will be open, and crews will flag traffic through the work area.
Howard County
Daylight Hours
Route T between Route 129 and Route 5 in Chariton County – Pavement patching will take place Monday, June 4 through Thursday, June 14. One lane will be open, and crews will flag traffic through the work area.
Laclede County
Overnight Hours
Interstate 44 between Route 133 and Route D in Phelps County – Roadway resurfacing continues.
* Guardrail repair and replacement will take place in various locations in the eastbound and westbound lanes the week of June 4.
* Bridge repair work in the westbound lanes at mile marker 172.8 in Phelps County will begin the week of June 4. One westbound lane will be open in the work area. The project is scheduled for completion in August.
Interstate 44 between Elm Street and Route 133 – Pavement patching will begin the week of June 4. One lane will be open through the work area. Project is scheduled for completion in November.
Daylight Hours
Interstate 44 between Route W and the Webster County line – Shoulder repair and roadway patching in the eastbound lanes continues. One eastbound lane will be open through the work area. The project is scheduled for completion in late June.
Route 5 between Route C and Farmer’s Lane – Roadway resurfacing and shoulder widening continues. One lane will be open, and crews will flag traffic through the work area. The project is scheduled for completion in August.
Route 32 between Route 5 and Route 17 in Texas County – Roadway resurfacing and shoulder widening continues. One lane will be open, and crews will flag traffic through the work area. The project is scheduled for completion in November.
Route JJ between Route F and Route T – Shoulder repair and culvert replacement will take place Monday, June 4 through Thursday, June 14. One lane will be open, and crews will flag traffic through the work area.
Interstate 44 Outer Road over Bear Creek, east of Heartwood Road – Bridge maintenance will take place Monday, June 4 through Thursday, June 7. One lane will be open, and crews will flag traffic through the work area.
Maries County
Daylight Hours
Route 42 between Route 63 and Route 17 in Miller County – Roadway resurfacing, shoulder addition, and guardrail installation continue.
* Crews will pave asphalt the week of June 4. One lane will be open, and crews will flag traffic through the work area. The project is scheduled for completion in November.
Miller County
Daylight Hours
Route 42 between Route 17 and Route 63 in Maries County – Roadway resurfacing, shoulder addition, and guardrail installation continue.
* Crews will pave asphalt the week of June 4. One lane will be open, and crews will flag traffic through the work area. The project is scheduled for completion in November.
Route BB between Route 42 and Route 133 in Maries County – Pavement patching will take place Monday, June 4 through Thursday, June 14. One lane will be open, and crews will flag traffic through the work area.
Moniteau County
Daylight Hours
Route W between Route 5 and Route E – Pavement patching will take place Monday, June 4 through Thursday, June 14. One lane will be open, and crews will flag traffic through the work area.
Phelps County
Daylight/Overnight Hours
Interstate 44 between Route D and Route 133 in Laclede County– Roadway resurfacing continues.
* Guardrail repair and replacement will take place in various locations in the eastbound and westbound lanes the week of June 4.
* Bridge repair work in the westbound lanes at mile marker 172.8 in Phelps County will begin the week of June 4. One westbound lane will be open in the work area. The project is scheduled for completion in August.
Route B over the Bourbeuse River, north of County Road 1400 – Bridge replacement continues.
* Grading work will continue the week of June 4. Minimal traffic interruptions are expected. The project is scheduled for completion in the fall.
Route D over the Burlington Northern/Sante Fe Railroad, east of Interstate 44 – Bridge replacement continues.
* Grading work will continue the week of June 4. Minimal traffic interruptions are expected. The project is scheduled for completion in the fall.
Daylight Hours
Route F between Route 68 and Route 72 – Roadway patching will take place Monday, June 4 through Thursday, June 14. One lane will be open, and crews will flag traffic through the work area.
Pulaski County
Daylight/Overnight Hours
Interstate 44 between Route 133 in Laclede County and Route D in Phelps County – Roadway resurfacing continues.
* Guardrail repair and replacement will take place in various locations in the eastbound and westbound lanes the week of June 4.
* Bridge repair work in the westbound lanes at mile marker 172.8 in Phelps County will begin the week of June 4. One westbound lane will be open in the work area. The project is scheduled for completion in August.
Daylight Hours
Route 17 between the Miller County line and the Texas County line – Pavement patching will take place Monday, June 4 through Thursday, June 14. One lane will be open, and crews will flag traffic through the work area.
Route 28 between Route 44 and the Miller County line – Pavement patching will take place Monday, June 4 through Thursday, June 7. One lane will be open, and crews will flag traffic through the work area.
Route TT between Big Piney Road and Route AW in Texas County – Asphalt repair will take place Monday, June 11 through Thursday, June 14. One lane will be open, and crews will flag traffic through the work area.
Washington County
Daylight Hours
Route P between Route 8 and Route C – Pavement repair will take place Monday, June 4 through Thursday, June 7. One lane will be open, and crews will flag traffic through the work area.
MoDOT encourages motorists to log on to www.modot.org/central to comment on their experiences traveling through highway work zones.
###