Update for Week of June 25
- Evergreen Street on west side of Glenstone Avenue CLOSED Monday night, June 25
Work Scheduled:
- Pouring concrete for street approach at Evergreen Street on west side of Glenstone Avenue
- Pouring concrete for outside lanes of Glenstone Avenue in areas between I-44 and Kearney Street
- Pouring concrete for outside lanes on Kearney Street at Glenstone Avenue
- Pouring concrete to rebuild street and business entrances in areas between I-44 and Kearney Street
- Pouring concrete to build medians in various locations
- Installing guardrail
- Applying pavement striping and installing traffic signal detector loops
- Rebuilding sidewalks in areas
Traffic Impacts:
- NIGHTTIME SIDE STREET CLOSING:
- Evergreen Street on west side of Glenstone Avenue CLOSED. Work hours: 6 p.m. to 6 a.m. Monday, June 25.
- Drivers urged to find alternate routes
- Outside northbound and southbound lanes of Glenstone Avenue closed at Kearney Street and at Kerr/Evergreen Street ‘round the clock
- Outside eastbound and westbound lanes of Kearney Street at Glenstone Avenue closed ‘round the clock
- NO RIGHT TURNS AT EITHER INTERSECTION
- By Wednesday, all lanes on Glenstone Avenue scheduled to open at Evergreen/Kerr Street intersection
- One northbound and one southbound lane of Glenstone Avenue remains open most of the time
- One eastbound and one westbound lane of Kearney Street remains open most of the time
- Drivers can expect delays on Glenstone Avenue between Kearney Street and I-44 until July 4
(Weather or construction delays could alter the work schedule.)
Project Summary:
- Rebuild the deteriorating concrete pavement on Glenstone Avenue in four separate locations
- At Kerr/Evergreen Street south of I-44
- At Kearney Street
- At the railroad overpass north of Commercial Street
- Between Lombard Street and Page Street
- Sections at Kearney Street and at Evergreen Street under construction from May 29 until July 4
- Sections at railroad overpass near Commercial Street and between Lombard Street and Page Street under construction starting in July or August
- Total Project Cost: $3.7 million
- Overall Completion Date: November 1, 2018
END
(For more information, call MoDOT in Springfield at 417-895-7600 or visit www.modot.org/southwest)
(Follow MoDOT's Southwest District: Facebook | Twitter | Instagram |YouTube)
(For timely traffic information in the Springfield area, visit www.ozarkstraffic.com)
Districts Involved
Southwest
Published On