Route 65: THE REBUILD Phase Two - Springfield

PROJECT DELAYED BY ONE WEEK UNTIL FRIDAY, JULY 13
  • CONTRACTOR DELAYED ON ANOTHER ROAD PROJECT CAUSING ROUTE 65 PROJECT TO START ONE WEEK LATER
  • I-44 at Route 65 in Springfield CLOSED 11:59 p.m. Friday, July 13, until 11:59 p.m. Saturday, July 14
  • Southbound Route 65 at I-44 in Springfield CLOSED 11:59 p.m. Friday July 13, until late August                                            

Work Scheduled:  

  • Removing southbound Route 65 bridge over I-44 beginning Friday night, July 6
  • Installing bridge column in I-44 median at southbound Route 65 

Traffic Impacts:  

  • I-44 CLOSED for 24-Hours: From 11:59 p.m. Friday, July 13, until 11:59 p.m. Saturday, July 14
    • Westbound detour: Northbound Route 65 to Valley Water Mill Road interchange (Farm Road 102) to southbound Route 65 to westbound I-44
    • Eastbound detour: Southbound Route 65 to Division Street to northbound Route 65 to eastbound I-44
  • SOUTHBOUND ROUTE 65 CLOSED: From 11:59 p.m. Friday, July 13, until late August
    • Southbound detour: Westbound I-44 to Glenstone Avenue (Exit 80) to eastbound I-44 to southbound Route 65
  • Nighttime lane closings possible on I-44 at Route 65 beginning July 6. Work hours: 8 p.m. to 6 a.m. 

(Weather or construction delays could alter the work schedule.) 

Project Summary:

  • Replace southbound Route 65 bridge over I-44 in Springfield
  • Rebuild southbound Route 65 pavement between Valley Water Mill Road (Farm Road 102) and Kearney Street in Springfield
  • Rebuild ramps:
    • Rebuild westbound I-44-to-southbound Route 65 ramp
    • Rebuild eastbound I-44-to-southbound Route 65 ramp
    • Rebuild southbound Route 65-to-Kearney Street ramp
    • Rebuild portion of eastbound I-44-to-southbound Route 65 ramp
  • Upgrade guardrail
  • Rebuild shoulders
  • No work planned for northbound Route 65
  • Prime Contractor: Millstone Weber, Inc. of St. Charles, Mo.
  • Completion Date: November 2018 (However, contractor plans to complete project by late August.)
  • Total Project Cost: $4.3 million 

END 

(For more information, call MoDOT in Springfield at 417-895-7600 or visit www.modot.org/southwest

(Follow MoDOT's Southwest District: Facebook | Twitter | Instagram |YouTube)

(For timely traffic information in the Springfield area, visit www.ozarkstraffic.com)

 

Districts Involved
Southwest
MODOT Newsroom

The newsroom is a one-stop shop for media partners to find their local and statewide communications contacts and news releases, as well as download department leadership portraits and other media.

Visit the Newsroom
Real Time Traffic

Monitor real time traffic with our online traffic map.