Pavement Sealing Work Scheduled on Stone County

Routes 160, JJ & H Beginning Week of July 9

Stone County – Three state routes in Stone County are scheduled to be sealed with a mixture of rock and oil beginning the week of July 9, the Missouri Department of Transportation said.

Here’s a look at the locations:

  • Route 160 between U.S. Route 65 and Missouri Route 13 (12 miles)
  • Stone County Route JJ from Missouri Route 86 north to the end of state maintenance (6 miles)
  • Stone County Route H from Route 13 west to the end of state maintenance (4.7 miles)
  • Stone County Route H from Route 39 east to the end of state maintenance (4.5 miles)

Weather and/or construction delays could alter the work schedule

Drivers can expect one-lane traffic with flaggers and pilot vehicles directing them through the work zone.  Traffic could be stopped for several minutes. Delays are expected. Drivers at side roads should wait for the pilot vehicle before entering the roadway.

Drivers are urged to use caution and reduce their speed when traveling over recently-sealed sections of highways.

A chip-seal is not an alternative to an asphalt overlay, but is planned for these roads as an economical way to maintain and preserve the roadway. The treatments keep a road from deteriorating and will extend its life.

Project information:

  • Contractor: Blevins Asphalt Construction Co., Mt. Vernon
  • Total cost: $1.6 million
  • Completion date: September 1, 2018 

 

(For more information, call MoDOT in Springfield at 417-895-7600 or visit www.modot.org/southwest)

(Follow MoDOT's Southwest District: Facebook | Twitter | Instagram |YouTube)

 

Districts Involved
Southwest
MODOT Newsroom

The newsroom is a one-stop shop for media partners to find their local and statewide communications contacts and news releases, as well as download department leadership portraits and other media.

Visit the Newsroom
Real Time Traffic

Monitor real time traffic with our online traffic map.